![PTI SENTRY TIM-100 Скачать руководство пользователя страница 5](http://html1.mh-extra.com/html/pti/sentry-tim-100/sentry-tim-100_installation-and-operation-manual_1623316005.webp)
Installation, Operation and
Serial Communication Programmer’s Guide
SENTRY
™
Tool Interface Module
(TIM-100/120)
and Program Module (TIM-200)
Section 2: Installation & Power-Up
12286 Rev 2
Page 1 of 4
2.1 Installation & Power-Up
The SENTRY TIM-100/120 is one component of the SENTRY exhaust control system. Please
follow the complete installation instructions for the specific controller.
CE Compliant Installation Note
To maintain CE compliance, if applicable, the SENTRY TIM-100/120 must be installed at a
height above the floor greater than 24” (0.6 meter).
Both the TIM-100 and TIM-120 are equipped with 4 holes for panel mounting as shown.
Power Requirements
The SENTRY TIM-100/120 operates using both positive and negative DC voltages. DC
Voltages may be supplied directly from the equipment via an interface cable or through a
stand-alone universal power supply (available from PTI).
Note:
•
In case of AC over-current situations, the SENTRY system relies upon the process
equipment for AC main disconnect.
•
The PTI Universal Power Supply, if used, provides additional DC short circuit current
protection with automatic reset
The DC Voltage supplies required for TIM-100/120 operation are:
1. Positive Voltage: + 15 to +24 VDC @ 650 mA
This voltage is used to power the electronic circuitry of the TIM-100/120 and
controller.