PROAIM 38ft BASE KIT
7
Attach 26.1ft cable to hook attached on 1st section of jib and another end with 3rd hook
attached to cable guide as shown below.
Then attach one end of 30.5ft cable to wire tensioner with hooks attached to 9th section
and another end with 2nd hook attached on 1st section.
Using the same approach attach another 30.5ft cable to wire tensioner on another side of
jib and one end with 3rd hook on 1st section.
Now pass both side cables through space on bottom of cable guide support rod as shown
below.
Attach 22.8ft cable to wire tensioner with hook attached to 9th section and another end
with hook on 3rd section.
Using same approach attach 2nd 22.8ft cable from another side and attach the end to 3rd
hook on 3rd section.
Pass both side cables (small) through space on top of cable guide support rod as shown be-
low.
Install the Head Platform assembly (leveling arm up) to the end of the smallest section with
the provided bolt, shaft collars, washers and nut. Tighten all the Allen bolts and nuts to
secure properly.
INSTALLING THE HEAD PLATFORM