Trident Series PD765 Process & Temperature Meters
Instruction Manual
11
Safety Information
•
Read complete instructions prior to installation
and operation of the meter.
•
Risk of electric shock.
•
Hazardous voltages exist within enclosure.
•
Installation and service should be performed only
by trained service personnel.
Installation
There is no need to remove the meter from its
case to complete the installation, wiring, and
setup of the meter.
Unpacking
Remove the meter from box. Inspect the
packaging and contents for damage. Report
damages, if any, to the carrier.
If any part is missing or the meter malfunctions,
please contact your supplier or the factory for
assistance.
Panel Mounting
•
Prepare a standard 1/8 DIN panel cutout – 3.622"
x 1.772" (92 mm x 45 mm). Refer to
•
Clearance: allow at least 4" (102 mm) behind the
panel for wiring.
•
Panel thickness: 0.04" - 0.25" (1.0 mm - 6.4 mm).
Recommended minimum panel thickness to
maintain Type 4X
rating: 0.06" (1.5 mm) steel panel, 0.16" (4.1 mm)
plastic panel.
•
Remove the two mounting brackets provided with
the meter (back-off the two screws so that there is
¼" (6.4 mm) or less through the bracket. Slide the
bracket toward the front of the case and remove).
•
Insert meter into the panel cutout.
•
Install mounting brackets and tighten the screws
against the panel. To achieve a proper seal,
tighten the mounting bracket screws evenly until
meter is snug to the panel along its short side.
DO NOT OVER TIGHTEN, as the rear of the
panel may be damaged.
Figure 1. Panel Cutout and Mounting
Mounting Dimensions
Figure 2. Meter Dimensions – Side View
Figure 3. Case Dimensions – Top View
1.76"
(45mm)
0.59"
(15mm)
3.2"
(81mm)
2.45"
(62mm)
3.6"
(91mm)