Commissioning - Page 19

FIG. 26 MAIN BURNER PRESSURES ADJUSTMENT

With the burner set to its correct pressure, the firing rate
given in TECHNICAL DATA should also be obtained and
this should be checked by meter reading at least 10
minutes after the main burner has been lit. When the
pressure and rate are correct, replace the adjustment
screw cover.

Shut down the boiler remove the pressure gauge and refit
the screw in the test nipple ensuring that a gas tight seal is
made.

Remove the self-adhesive arrow from the inspection ticket
tied to the burner supply pipe and stick it to the Data Plate
inside the controls cover to indicate the appropriate burner
setting pressure.

Refit the controls cover, and secure with screw.

Relight the boiler and heat the system to maximum. Check
for water leaks, turn the boiler off, drain the system whilst
hot.

Refill the system and on sealed systems adjust to the
correct cold fill pressure. Set the pressure gauge pointer to
the system design pressure.

If a by-pass circuit is fitted the by-pass valve should be
adjusted with the boiler operating under minimum load
conditions to maintain sufficient water flow through the
boiler to ensure that the overheat thermostat does not
operate under normal operating conditions.

Pilot Burner

The pilot is pre-set and no adjustment is required. The pilot
flame envelope should cover the electrode tip and spark
earthing strip see FIG. 30. If the pilot flame is not as
illustrated, remove and clean the pilot as described in the
Servicing Instructions Section 3, PILOT BURNER, Page
22.

Boiler Thermostat

At its minimum and maximum settings, the thermostat
should control the water flow temperature at approximately
55ºC-82ºC (130ºC-180ºF).

The thermostat has been calibrated by the makers and no
attempt should be made to re-calibrate it on site. Turn on
the boiler thermostat and ensure that the main burner is
alight. Turn the thermostat to the ‘O’ position and check
that the main burner shuts down.

Gravity Hot Water/Pump Over-Run Thermostat

The function of this thermostat is determined by the
position in which the GRAVITY/FULLY PUMPED SYSTEM
selection switch is set. The thermostat is preset and no
adjustment is possible.

On the FULLY PUMPED switch position it will operate as a
pump over-run thermostat and will keep the pump running
after the boiler has shut down, as long as the water
temperature within the boiler is above approximately 80ºC.

On the GRAVITY switch position it will operate in series
with the boiler thermostat when only the gravity domestic
hot water circuit is in operation.

It will over-ride the boiler thermostat when the water
temperature within the boiler is above 80ºC.

Overheat Thermostat

The overheat thermostat is pre-set and no adjustment is
possible. It will require manually resetting if an overheat
condition occurs. Access to the reset button is through a
hole in the underside of the controls cover, see
FIG. 2.

NOTE:

 Interruption of the electrical supply to the boiler may

also cause the overheat limit thermostat to operate.

Other Boiler Controls

All boiler mounted controls are designed so that if any fault
should occur they will fail safe. No further setting or
checking is necessary.

External Controls

Check that any other external control connected in the
system, such as clocks and thermostats, control the boiler
as required.

User’s Instructions

A User’s Instructions leaflet is provided with this boiler but
the householder must have the operation of the boiler and
system explained by the Installer. The householder must
also be advised of the importance of annual servicing and
of the precautions necessary to prevent damage to the
system and building, in the event of the system remaining
out of commission in frost conditions.

Содержание Profile

Страница 1: ...ating spares co Tel 0161 620 6677 lOOe fanned balanced flue gas fired boiler THIS APPLIANCE IS FOR USE WITH NATURAL GAS G20 ONLY Installation and Servicing Instructions LEAVE THESE INSTRUCTIONS ADJACENT TO THE GAS METER ...

Страница 2: ...ed on INDIRECT hot water systems only The cast iron heat exchanger is suitable for use on open vented gravity domestic hot water pumped central heating systems or fully pumped systems which may be sealed or open vented The boiler can be supplied with either of the following types of flue system these are packaged with the terminal and associated flue components 1 Standard Horizontal flue system Pa...

Страница 3: ... British Standards and Codes of Practice B56798 B55440 Part 1 B55440 Part 2 B55449 Part1 BS5546 B54814 B56891 BUILDING REGULATIONS MODEL WATER BYELAWS BRITISH GAS PUBLICATION DM2 GAS SAFETY INSTALLATION AND USE REGULATIONS BUILDING STANDARDS SCOTLAND REGULATIONS BOILER DIMENSIONS Page 3 SITE REQUIREMENTS Page 3 The boiler is not suitable for external installation and should not be fitted directly ...

Страница 4: ...Supplied By www heating spares co Tel 0161 620 6677 4 Site Requirements Page 4 FIG 2 GENERAL ARRANGEMENT ...

Страница 5: ...a of 349 cm2 54 in2 Further details for installation of a boiler within a compartment are giving in BS 6798 If the openings draw air from outside the building the free areas may be halved Refer to BS 54401 Part 2 for further guidance Balanced Flue Terminal and Ducting The fresh air inlet and flue ducts can be run from either the left right rear or top of the boiler to a miniature terminal on the o...

Страница 6: ...he boiler and its associated equipment should be controlled by a 3A fused double pole switch having at least 3mm contact separation in both poles so that complete isolation from the supply can be achieved to enable servicing work to be carried out in safety TECHNICAL DATA Page 6 Maximum working head 30 5m 100 ft Power consumption 80 watts excluding pump Minimum working head on Fully Pumped systems...

Страница 7: ...in the system the resistance through them quoted in their manufacturer s literature must be taken into account The pump may be fitted on either the flow or return and MUST be wired directly to the boiler terminal block see FIG 24 It must be fitted with two isolating valves which are positioned as close to the pump as possible Closing of any valve must always leave the open vent unobstructed TABLE ...

Страница 8: ... over run thermostat This will ensure that the pump will continue to run after boiler shut down if the water temperature in the boiler is high If a three port diverter valve is used as shown in FIG 6 a by pass is not necessary since one circuit is always open temperature in the boiler is high thus preventing nuisance operation of the overheat thermostat If a three port diverter valve is used as sh...

Страница 9: ...side of all heat emitters been made for the extension Where a vessel of the or calculated size is not available the next available larger size should be used The boiler flow temperature is ii where access to a make up vessel would be controlled at approximately 82ºC difficult by using the mains top up method or a remote automatic pressurisation and make up unit as sillustrated in FIG 7 METHODS 1 a...

Страница 10: ...Supplied By www heating spares co Tel 0161 620 6677 10 Technical Data Page 10 Fig 7 Fig 8 ...

Страница 11: ... in Separate Cartons Fig 9 TEMPLATE Place template in proposed boiler position ensuring it is level the minimum side clearances are automatically allowed for REAR FLUING Mark holes A B D age flue outlet hole and side of boiler reference lines through slots C SIDE FLUING Mark holes positions A D and side of boiler reference lines through slots C Extend Horizontal line from top of the boiler to side...

Страница 12: ... Take air flue duct assembly and measuring from the flanged end mark and cut the outer air duct and inner flue duct to dimension Y plus 45 mm Ensure that both ducts are cut squarely NOTE Cutting length remains the same for minimum or maximum clearance at the rear of the boiler Fig 12 AIR FLUE DUCT ASSEMBLY 1 Slide rope sealing ring on to air duct 2 Engage the terminal on to the ends of the inner f...

Страница 13: ...ver forward 10mm lower to release from the four side fixings and pull forward clear of the thermostat knob Remove door by undoing the two lower fixing screws and lift door off the two upper hinge brackets Remove the screws securing the combustion chamber front panel and remove panel Disconnect the fan supply leads from the connector adjacent to the fan Leaving in place the three screws identified ...

Страница 14: ...and secure using four wing nuts accessory pack F Fig 17 SECURING BOILER Rotate the left hand adjustment screw to align one of the holes in the base plate with hole D in the wall Working through the hole in the leg secure the base plate to the wall using the screw from accessory pack D Make good the wall surface around the flue terminal Fit optional terminal wall plate if required Fig 18 FLUE ELBOW...

Страница 15: ... recommended A drain off tap should be installed close to the boiler if it is in a low point of the system On combined gravity hot water pumped central heating installations the flow and return pipes for both the gravity hot water circuit and pumped central heating circuit must be connected to tees fitted directly to the flow and return pipes on the boiler The gravity circuit should be installed i...

Страница 16: ...ulb through grommet retaining hole then attach to return pipe using spring clip contained in auxiliary pack 5 Refit grommet ensuring that it makes a good seal around the capillary Ensure that the capillary is secure in clips provided Refer to Fig 2 6 ENSURE that the system change over switch in the control box is set in GRAVITY DHW position ELECTRICAL The boiler and all external control circuit wi...

Страница 17: ...rnal gravity domestic hot water control circuit to terminal marked MAINS SwL Switched live from external pumped central heating control circuit to terminal marked MAINS L Neutral to terminal marked MAINS N Earth to terminal marked adjacent to cable clamp See NOTE If there are no external controls fitted connect the SwL and L terminals to permanent live in the junction box NOTE Ensure that the eart...

Страница 18: ...two fixing screws Remove the temporary label from the front of the casing having checked compliance with the information it contains First Lighting WARNING Before lighting the boiler ensure that the CASE DOOR HAS BEEN CORRECTLY FITTED and that the sealing strip fitted to the case door is forming a tight seal with the main boiler casing Before proceeding to light the boiler check that the external ...

Страница 19: ...y the makers and no attempt should be made to re calibrate it on site Turn on the boiler thermostat and ensure that the main burner is alight Turn the thermostat to the O position and check that the main burner shuts down Gravity Hot Water Pump Over Run Thermostat The function of this thermostat is determined by the position in which the GRAVITY FULLY PUMPED SYSTEM selection switch is set The ther...

Страница 20: ...Supplied By www heating spares co Tel 0161 620 6677 20 Commissioning Page 20 Fig 27 FUNCTIONAL FLOW DIAGRAM Fig 28 BOILER WIRING DIAGRAM ...

Страница 21: ...ain access to the flueways in the heat exchanger for cleaning The following notes apply to the boiler and its controls but it should be remembered that attention must also be paid to the heating circuit itself including radiator valves thermostats the time control and the expansion and feed water system It is advisable to clean the boiler immediately after the end of the heating season In all case...

Страница 22: ... adapter each being identified with a red ring 3 PILOT BURNER The following operations are only necessary if the pilot flame is distorted or the wrong size i e too small A Unscrew the steel pilot tube from the pilot assembly Take care not to damage the electrode B Unscrew the two hexagonal head screws securing the pilot and shield to the main burner and remove the pilot assembly be careful that th...

Страница 23: ...sconnect the electrical supply from the gas valve Note White Rodgers has individual Wire positions Refer to FIGS 27 and 28 5 Unscrew the union connecting the pilot supply pipe to the gas control valve 6 Separate the gas control valve from the flange at the outlet port by removing the securing screws remove two M4 screws retaining valve support bracket unscrew gas inlet assembly at valve Note The S...

Страница 24: ... 4 Disconnect six way plug two way plug and electrode lead from the electronic control Refer to FIGS 27 28 Disconnect the flying leads of the electronic control as follows white wires from the control thermostat brown wire from overheat thermostat blue wire from boiler terminal block connection N green yellow wire from earth post 5 Release the control by lifting it from the four retaining lugs 6 R...

Страница 25: ...at bulb to the flow pipe 13 Remove the split grommet in the base of the boiler and the split grommet in the fan chamber Feed the capillary and bulb through the holes 14 Replacement is the reverse of removal The bulb of the new thermostat should be coated with heat conducting paste Ensure the rubber grommets in the base of the boiler and the fan chamber make a good seal around the capillary 15 Ensu...

Страница 26: ...Supplied By www heating spares co Tel 0161 620 6677 26 Servicing Instructions Page 26 Fig 31 FAULT FINDING CHART ...

Страница 27: ... Control Valve Kit White Rodgers 907702 382 988 10 Gas Control Valve Kit S I T 909029 289 396 11 Gas Manifold O Ring 401637 337 467 12 Gravity DHW Pump Over Run Thermostat CL8 P1510 404501 382 967 13 Flue Elbow Sealing Gasket 212084 337 424 14 Electronic Control 407677 382 462 15 Fuse 1 amp 641903 336 585 16 Thermostat Knob 225251 337 370 17 Pressure Switch 642216 385 887 18 Fan 409573 337 860 19 ...

Страница 28: ...ritation Irritation to respiratory tract Precautions People with a history of skin complaints may be particularly susceptible to irritation High dust levels are only likely to arise following harsh abrasion In general normal handling and use will not present discomfort follow good hygiene practices wash hands before consuming food drinking or using the toilet First Aid Medical attention must be so...

Отзывы: