Installation | Flushing the System
56
Cooling Pad | Installation and Operation Guide Rev B | Doc P/N: 080205039E
3.7 Flushing the System
To flush the system before starting it up for the first time, do the following:
1. Make sure that the cleaning plug (25) and valve (61) are closed.
2. Fill the reservoir channel with water to 3/4 capacity.
3. Open the valve (61) and empty the water from the reservoir to remover
the debris from installation.
4. If needed, repeat steps 1-3.
5. Repeat step 1-2.
6. Verify that the drainage valves (11) and maintenance valve (A) are open.
7. Turn on the pump manually.
8. Flush the system for two minutes.
9. Close the drainage valves (11).
10. Repeat step 8.
11. Turn on the pump.
12. Check the reservoir channel and the filters. If needed, perform a
cleaning according to step 3.
13. When done, repeat steps 1-2.