INSTALLATION & OPERATIONAL SSHLV SERIES MANUAL
ON
O
FF
PUSH BLUE HANLDE IN
2.11.
INITIAL ADJUSTMENTS
After your appliance has been properly installed as described in the installation section of this
manual, it will need to be adjusted to ensure that it will perform as designed. A qualified person must
perform these adjustments.
To perform these adjustments the following tools will be needed:
Manometer
Digital Thermometer (Temperature Probe)
DC Microammeter
DC Voltmeter
2.11.1. FILLING THE APPLIANCE
Refer to the following procedure to fill the cook tank prior to
operation.
1. Ensure that the drain valve is closed.
2. Fill the tank with oil/shortening until the oil/shortening
reaches the level line(s). Never let the oil/shortening level
go below the MIN LEVEL mark stamped on the tank.
2.11.2. LIGHTING INSTRUCTIONS
There is nothing to manually light on the SSHLV system. Pilot ignition is performed and controlled
by the electronic ignition system. Refer to the following instructions to light the appliance.
1. Open the gas supply valves to the appliance.
2. Turn the gas valve knob to the ON position.
3. Turn the controller on.
Press the
* button to turn the COMPUTER on.
*
4. The main burners will light and be controlled by the computer.
Note: If your appliance has a self cleaning burner system, the burners may make a
popping sound immediately after the main burners light during startup. This noise during
startup is part of the normal operation of the self cleaning burner system and should NOT
continue during normal cooking & idle periods. (SCB Only)
WARNING
Oil/shortening must completely cover the heat tubes at all times while appliance is on.
CAUTION
This appliance is not designed for cooking with water. Fill with oil/shortening only.
WARNING
During operation there is an open flame inside this appliance. The unit may get hot enough to
set near by materials on fire. Keep the area around the appliance free from combustibles.
L20-407 rev. 2 (12/14)
11