3.3 CONTROL OF THE INTERNAL TIGHTNESS 
 
The valve internal tightness may be checked by placing the valve in full close position,  keeping 
the line pressure upstream from the valve and checking that there is not fluid leaks  downstream 
from the valve and from the pilot blowdown. 
 
3. 4 

COMMISSIONING ( INSTALLATION ACCORDING TO DIAGRAM IN FIG. 3 ).

 

a)  On  the  data  plate  check  that  the  required  intervention  value  is  within  the  listed  limits  ( Wao 
value on the plate ) 
b) Fully tighten the adjusting ring nut of the setting on the pilot 
c) make sure that the pressure upstream from the cut-off valve is lower than the intervention value 
d) slowly open the cut-off valve  
e) check the tightness of all the joints placed under pressure with the previous operation 
f) increase the pressure up to the intervention value, slowly unscrew the ring nut until the pilot pipe 
starts to discharge the gas. 
h) very carefully carry on  the previous operation until the valve  opening 
i) decrease the pressure and check that the pilot valve is close again and their tightness. 

3. 5  

COMMISSIONING ( INSTALLATION ACCORDING TO DIAGRAM IN FIG.4 )

 

a) With the same order carry out the operations a, b, c, d, e, of paragraph 3.4  
b)  Connect  the  C  way  of  the  three-way  switch  valve  (  PUSH  )  to  a  chamber  with  controlled 
pressure  
c) stabilize the test pressure in the chamber at the same value as the pressure at the safety valve 
inlet 
d) actuate the three-way valve by connecting the controlled pressure chamber to the pilot sensing 
line. 
e) increase the test pressure in the controlled chamber up to the intervention value of the safety 
valve 
f) with the same order repeat the operations g,h, of the previous paragraph. 
g) decrease the pressure and check that the pilot valve is close again and their tightness. 
h) restore the three-way valve position in order to connect the chamber to be controlled with the 
pilot sensing line. 

                                 | [email protected] | Phone: 877.566.3837 | Fax: 925.407.2903

Содержание PVS 782

Страница 1: ...1 SAFETY RELIEF VALVE PVS 782 TECHNICAL MANUAL MT 014 INSTRUCTIONS FOR THE INSTALLATION ENTRY INTO SERVICE AND MAINTENANCE sales mvandc com Phone 877 566 3837 Fax 925 407 2903 www mvandc com...

Страница 2: ...F USE 3 0 COMMISSIONING 3 1 PRESSURIZZATION 3 2 INSPECTION OF THE EXTERNAL TIGHTNESS 3 3 INSPECTION OF THE INTERNAL TIGHTNESS 3 4 COMMISSIONING INSTALLATION ACCORDING TO DIAGRAM IN FIG 3 3 5 COMMISSIO...

Страница 3: ...ations In FIGURE 1 the valve functional diagram is illustrated 1 1 MAIN SPECIFICATIONS The PVS 782 valves are safety accessories fit for the use on preliminary treated non aggressive gaseous fluids Su...

Страница 4: ...4 Figure 1 sales mvandc com Phone 877 566 3837 Fax 925 407 2903...

Страница 5: ...nection 10 connection pipe 11 spring 12 ring nut 13 safety diaphragm 14 rod 15 spring 1 2 VALVE CONTROL The PVS 782 valve is a pilot operated valve therefore the valve opening and closing operations a...

Страница 6: ...6 Figure 2 sales mvandc com Phone 877 566 3837 Fax 925 407 2903...

Страница 7: ...lues very near to the intervention values Until the controlled pressure is lower than the setting value the spring action 5 prevails on the value of the fluid thrusts on the diaphragm 4 and the plug p...

Страница 8: ...the ring nut 12 inside the pilot and by using different springs according to the predetermined setting value The spring 11 allows the extra stroke of the spring diaphragm unit without loading the plug...

Страница 9: ...e lifting devices are fit for the loads to be lifted lifting capacity and functionality The handling of the equipment shall be carried out by using the lifting eyes arranged on the equipment itself Th...

Страница 10: ...justed at the required intervention value lead seals may be carried out at the factory directly by the manufacturer or on site by the user 2 3 SPECIAL INSTRUCTIONS Before installing the valve it is ne...

Страница 11: ...rrange a protection end against water and nesting The connections to the inlet and outlet pipelines are carried out by means of standardized flanges the sizes and types of which are showed on the data...

Страница 12: ...12 Legend of Figure Dimensioni d ingombro overall dimensions peso in kg weight in Kg sales mvandc com Phone 877 566 3837 Fax 925 407 2903...

Страница 13: ...13 Figure 3 Not included in our supply Discharge to the atmosphere Cut off valve sales mvandc com Phone 877 566 3837 Fax 925 407 2903...

Страница 14: ...14 Figure 4 sales mvandc com Phone 877 566 3837 Fax 925 407 2903...

Страница 15: ...ls written on the plate is the following Safety valve valve model Cg flow rate coefficient where foreseen S n serial number PS max permissible pressure DN valve nominal diameter Flange type of flange...

Страница 16: ...user shall take proper precautions in order to limit the effects of such events on the assembly when these are expected 3 0 COMMISSIONING 3 1 PRESSURIZATION After the installation check that the conn...

Страница 17: ...ischarge the gas h very carefully carry on the previous operation until the valve opening i decrease the pressure and check that the pilot valve is close again and their tightness 3 5 COMMISSIONING IN...

Страница 18: ...o the provisions in force on the place of installation and depending on the needs perform a preventive maintenance of the valve and of its pilot The periodical inspections concern also the state of th...

Страница 19: ...in paragraph 5 4 3 REASSEMBLY Reassemble the parts by referring to the signs put on the parts during the disassembly so that all the connections match correctly 5 0 LUBRICATION The valves are already...

Страница 20: ...ay from direct sun light in order to avoid a fast aging 7 0 SPARE PARTS For the spare parts please refer to the spare part lists SR 164 Valve PVS 782 SR 182 1 Pilot P 15 P 15 A SR 182 2 Pilot P 16 P 1...

Отзывы: