7 Commissioning
Before commissioning the machine, it must be thoroughly cleaned and then
oiled., see chapter
9
Care and maintenance
in the instruction manual.
●
Check the machine, particularly its electrical wiring and pneumatic tube
connections, for any damage.
●
Have skilled personnel check if the machine can be operated with the available mains vol-
tage.
Do not operate the machine if there is any discrepancy.
The machine may only be connected to an earthed socket!
●
In the case of machines with PicoDrive and
P45 PD2-L
control unit, have specialists
check the basic position of the machine drive before commissioning the machine (see
Chapter
7
.
02
Basic position of the machine drive
).
7
.01
Switching the machine on/off
●
Switch the machine on (see Chapter
7
.
01
,
On/off switch
in the instruction manual).
Commissioning