Ground Fix Installation 

(1.1) 

 

 

Components: 
 
2 Treated Posts 
90x90x2000  

Ground Fixed 

BS EN 1176

  

Freechimes  

Alto/ Soprano 

Page 3 of  3 

Excavate 2 holes with a 250mm diameter

tapering down to 350mm diameter and
650mm depth

Compact base of hole with 50mm of
aggregate. Lower ground Fix posts
attached to instrument into hole (check
instrument straight and level, and at
correct height before filling with
concrete)

Carefully lay 2 x legs on a level surface.
Line up pre drilled holes in the
backboards with the legs and ensure the
instrument is aligned square with the
legs. Fix in place using 8x70mm screws
supplied

Fill holes with fast drying concrete to
manufacturers specifications. If posts
protrude above instrument they can be

cut down

6

50

350

250

50

6

00

Foundations should not present a hazard. These foundations are 
recommended as a guide, for more information on foundation 
details for various surface see Part 7 of BS EN 1176. 

Options for finishing wooden posts: 
A - Dig the posts in deeper than recommended minimum depth to avoid cutting off excess post protruding above chimes. 
B - Dig post into recommended depth, set height of chimes and cut excess post protruding above chimes, but exposed end grain will need treating. 

Metric Conversion: 
50mm/ 2” 
250mm/ 10” 
350mm/ 14” 
472mm/ 1 ft   6 

37

/

64

 “ 

600mm/ 24” 
650mm/ 26” 
709mm/ 2 ft   3 

29

/

32

 “ 