– 8 –
ix. CUTTING HEAD
INSTALLATION
x. SIDE TABLE & SPLASH GUARD
INSTALLATION
1.
Slide the motor into the body of the cutting head
mainframe, holding the motor front (outer) ring
insert into the mainframe bracket.
2.
Holding the cutting head steady, insert 4 bolts onto
the front end of the motor through the cutting head
mainframe. Lock the bolts tight to hold the motor in
position.
3.
Insert the inner flange onto the blade shaft against
the motor’s front end.
4.
Place the blade onto the shaft making sure the
directional arrows are pointing in the direction of the
shaft rotation. Secure in place with the outer flange
and blade shaft nut.
5.
Insert the main long bolt in the upright of the front
plate while holding the cutting head mainframe, lock
it tight in position. Insert the second long bolt into
the height adjustment slot and lock it tight in
position. Place the tension spring into position for
height adjustment.
See figure 2.
1.
Install the side table and splash guard as shown in
figure 3
to the side. Fasten the screws respectively
to the saw frame.
1.
Remove the water pump from the box and check that
it is not damaged.
2.
Place the pump into the bracket at the right front
corner of the water tray along its side so that the
water outlet is positioned horizontally. Connect the
water hose from the blade guard to the pump and
plug the power cord into the 3-prong receptacle.
3.
Fill the water tray so that the water intake is fully
immersed.
4.
Be sure to support the pump during installation to
prevent pump failure or damage.
Figure 2
Figure 3
Figure 4
xi. WATER PUMP INSTALLATION
Disconnect the pump
before attempting to handle the pump.
Never operate pump without water in
the tray.
WARNING!
Содержание VXRS RAIL SAW