Parker EP Series Pro-Bloc Скачать руководство пользователя страница 7

Installation and Operation Manual 

EP Series Pro

-B

loc

®

IPDE-IOM-EP-SERIES-PROBLOC 

Page 

6

 of 10 

ECO-0364767 

Rev: - 

The secondary and vent are then closed (the primary valves is already closed) and the instrument safely 
removed.  

The double block gives two isolations to prevent process escape while the instrument is removed. Once 
the instrument is calibrated or replaced with a new one it can be fitted back on top of the valve outlet 
and the primary and secondary valves opened again to allow pressure measurement to continue. 

It is  possible to calibrate a pressure transmitter  without removing  it; this  is  in  situation  calibration 
commonly called “in-situ” calibration. To do this you follow the above procedure to vent the valve. Then 
a known pressure is pumped into the open vent, a handheld device is then connected to the back of 
the  transmitter  with  electrical  leads  after  removing the cover.  If  the  known  pressure from  the  pump 
agrees with the electrical reading from the transmitter it is in calibration and the measuring equipment 
removed, then the valves are returned to their operating positions. 
If however the readings do not agree, the measuring device has the ability to electronically change the 
reading  to  make  it  agree  with  the  known  pressure,  this  is  done  by  turning  a 

k

nob  clockwise  or anti 

Содержание EP Series Pro-Bloc

Страница 1: ...Effective July 2018 IPDE IOM EP SERIES PROBLOC Effective April 2021 Installation and Operation Manual EP Series Pro Bloc...

Страница 2: ...res Before installation ensure that all valves are in the closed position Parker Pro Bloc uses standard flange connections For connection please refer to the appropriate installation standard for the...

Страница 3: ...op pin Ball valves should always be fully open or fully closed Do not leave in a mid position Three way vent ball valves red handle have no firm centre off position and are positioned visually Needle...

Страница 4: ...f 10 ECO 0364767 Rev Installation and Operation Manual EP Series Pro Bloc IPDE IOM EP SERIES PROBLOC ISOLATE VALVE OPERATING POSITIONS ISOLATE BALL VALVE IN CLOSED POSITION ISOLATE BALL VALVE IN OPEN...

Страница 5: ...of 10 ECO 0364767 Rev Installation and Operation Manual EP Series Pro Bloc IPDE IOM EP SERIES PROBLOC BALL VENT VALVE OPERATING POSITIONS VENT BALL VALVE IN CLOSED POSITION VENT BALL VALVE IN OPEN PO...

Страница 6: ...position during normal operating conditions allowing the process pressure to enter the gauge or transmitter to perform its function to give a pressure reading The words Primary and Secondary are prin...

Страница 7: ...a pressure transmitter without removing it this is in situation calibration commonly called in situ calibration To do this you follow the above procedure to vent the valve Then a known pressure is pum...

Страница 8: ...r operating positions Vent plug The valve is shipped with a vent plug loose or installed as per the client s requirements While venting the valve this plug must be removed The plug can be replaced for...

Страница 9: ...handle locking nut Handle may be removed To re install the handle for valve operation Ensure shaft and nut threads are free from contaminants including any used thread locker Replace handle Apply Bon...

Страница 10: ...tance is evident when operating the valve handle Adjustment to the gland can be carried out to prevent leakage Replacement bonnets are available H series Needle Valve Gland Adjustment CAUTION Adjustme...

Страница 11: ...direction to stop lightly on seat max 2 Nm 2 Open the valve one full turn by rotating the handle in a counter clockwise direction 3 The two bridge nuts on either side of the spindle must be tightened...

Отзывы: