DTX10 - DTX80 USER GUIDE

4.   

Sequence of Operation

The sequence is controlled by a Solid State Timing and Relay circuit (Sequence Annunciator) which in turn 
controls five electric solenoid valves. The first four are 3-Way Normally Closed Valves, which supply control 
air to operate air operated switching inlet and exhaust valves. The Inlet Valves are Normally Open and are 
closed by supplying dry control air to the valve actuator. The Exhaust Valves are Normally Closed and are 
closed by supplying dry control air to the valve actuator. The fifth solenoid is the repressurization valve. 
There are also four mechanical check valves, two outlet and two purge, that allow for proper air flow.

STEP 1- LEFT DRYING; RIGHT REGENERATING 

SOLENOID #1 is de-energized sending no air to Exhaust Valve #1 (left side). Exhaust Valve #1 is closed.

SOLENOID #2 is de-energized sending no air to Inlet Valve
#1 (left side). Inlet Valve #1 is open. All of the wet inlet air is flowing through Inlet Valve #1. It is dried as it 
passes through the left tower desiccant bed and exits out the left side Outlet Check Valve to the dryer out-
let. The left tower is the Drying tower and the associated pressure gauge should read line pressure,.

At the same time SOLENOID #3 is energized sending a signal to Inlet Valve #2 (right side). Inlet Valve #2 is 
closed, preventing inlet air flow through the right tower.

SOLENOID #4 is energized sending a signal to Exhaust Valve #2 (right side). Exhaust Valve #2 is open. 
(NOTE: When exhaust valve first opens, the associated tower will depressurize from line pressure to atmo-
spheric pressure.) Purge air will now flow from the dry air outlet through the Purge Adjusting valve, Purge 
Orifice and the right hand Purge Check Valve. This purge air then proceeds through the right tower near 
atmospheric pressure, removing the moisture and exiting the right hand Exhaust Valve and Muffler in vapor 
form (at no time should the dryer expel any significant amount of liquid water from the muffler; this is a sure 
sign of trouble in the system). The right tower is the regenerating tower, the associated pressure gauge 
should read “0” PSIG.

SOLENOID #5 is de-energized and closed.

STEP 2 - LEFT DRYING, RIGHT REPRESSURIZING

While the left tower is still drying, Solenoid #4 will de- energize, relieving the control air signal on the right 
exhaust valve, returning that valve to its normally closed state. Closing this valve keeps air in the tower, al-
lowing the depressurized part of the dryer to build up pressure or “repressurize”. At the same time Solenoid 
#5 is energized and opened, providing additional air to the tank coming from the purge line to ensure full 
repressurization of the dryer.  Prior to switching towers, all of the gauges should equalize to line pressure.

STEP 3 - LEFT REGENERATING, RIGHT DRYING

Step 3 is the reverse of step 1. Solenoid #1 is energized, providing control air to and opening the left ex-
haust valve.

Solenoid #2 is energized, providing control air to and closing the left inlet valve. Solenoid #3 and #4 are 
de-energized. Thus the right inlet is open, and the right exhaust is closed. All the wet air is now flowing 

through the right tower and is being dried at line pressure. The left tower is being regenerated at 
atmospheric pressure. Solenoid #5 is de- energized and closed.

STEP 4 - LEFT REPRESSURIZING, RIGHT DRYING

 

Step 4 is the reverse of Step 2. Solenoid #1 de-energizes, allowing the left exhaust valve to close and al-
lowing the dryer to repressurize. In addition, Solenoid #5 energizes providing additional air for repressuriza-
tion.

NOTE: The Purge Gauge (middle) should read purge pressure, except during repressurization. Purge pres-
sure for standard inlet design conditions is listed on page 4. For other than standard or design conditions 
consult the factory.

Содержание DTX 10

Страница 1: ...Heatless High Pressure Desiccant Dryers User Guide Models DTX10 DTX80...

Страница 2: ...ruction manual for the use of the Parker Dryer Information is given not only for the user but also for the technical personnel who may repair the dryer in the event that this is ever necessary It is r...

Страница 3: ...lacement 14 9 2 Inlet and Exhaust Valve Repair 15 10 Parts general parts description 16 11 Troubleshooting Guide 17 12 High Humidity 19 12 1 Principle of Operation 19 12 2 System Components 19 12 3 Ca...

Страница 4: ...between 35 F and 100 F Dryer should be located in an area accessible for maintenance Location should be clean cool with a level vibration free floor Location of receiver may vary depending on particu...

Страница 5: ...the regenerating tower and must be up sized accordingly It is recommended that the exhausts be piped separately for ease of troubleshooting and maintenance Before any attempt is made to operate the dr...

Страница 6: ...able regulations NOTE Desiccant contaminated with oil or other foreign substances may be covered under disposal regulations for the contaminant Desiccant dryers work on the principle of adsorption Ads...

Страница 7: ...Flow Dryer outlet flow is equal to the dryer inlet flow minus the purge flow Air Out Air In Main Exhaust DTX Series Flow Schematic MODEL CAPACITY PSI CFM COLOR SIZE DES TOWER IN OUT CON DTX 10 50 no g...

Страница 8: ...atmospheric pressure removing the moisture and exiting the right hand Exhaust Valve and Muffler in vapor form at no time should the dryer expel any significant amount of liquid water from the muffler...

Страница 9: ...e dryer bypass valve Bypass valves must be bubble tight to prevent moisture from migrating around the dryer and contaminating the dry air outlet It is required that the dryer be started without the mu...

Страница 10: ...hould be used Flow direction is Upflow Drying Downflow Purge Switching Failure Alarm is optional and the dryer must be operating over 70 PSI for proper function of the alarm Dryer valving is fail safe...

Страница 11: ...ter Package dryers open manual ball valves on filters to allow full depressurization Leave ball valves on filters open while servicing Without the Basic Filter Package close control air filter off Rem...

Страница 12: ...Annunciator The Variable Cycle Control Switch must be set to 100 load setting for the DDS to work If the dryer is maintaining a good dew point AFTER the first five minutes of drying the DDS will over...

Страница 13: ...producing clean dry air Although the probe can be exposed to occasional brief periods of liquid saturation it can not be exposed to continuous wet conditions If your dryer is over loaded and saturated...

Страница 14: ...the dryer Semi Annually 1 Inspect desiccant for physical condition Desiccant from a freshly regenerated bed should be white dry to touch and of consistent size and shape 2 Check and clean mufflers Thi...

Страница 15: ...tance may require different procedures than desiccant replaced strictly due to aging NOTE Use only manufacturer supplied desiccant which is a high capacity high quality desiccant designed and sized fo...

Страница 16: ...area where mufflers would not be required G PURGE CONTROL REGULATOR OR VALVE Furnished to adjust and regulate purge flow for regeneration H SOLID STATE CONTROLLER SEQUENCE ANNUNCIATOR PANEL Furnished...

Страница 17: ...et or Exhaust Valves 1 Control air shutoff valve closed Open 2 Control air filter dirty Replace Element 3 Leak in control air tubing Repair 4 Control solenoid defective Repair or replace 5 No output f...

Страница 18: ...Valves 1 Control air shutoff valve closed Open 2 Control air filter dirty Replace Element 3 Leak in control air tubing Repair 4 Control solenoid defective Repair or replace 5 No output from controlle...

Страница 19: ...ive humidity condition 20 F 12 2 System Components POWER 12 220 VAC 10 50 60Hz 1 Watt DIMENSIONS PC Board 3 5 x 2 75 x 1 1 inches OPERATING TEMPERATURE 15 F 9 4 C to 140 F 60 C STORAGE TEMPERATURE 40...

Страница 20: ...and dryer system may require 48 hours or more to reach desired dew point on initial or subsequent start ups High humidity alarms should be disregarded until this time 8 The unit is normally factory se...

Страница 21: ...It is imperative that the isolation valve be fully open so that the DDS reads pressure dew point The sample line is fitted with coiled capillary tubing to control the sample air flow There must be con...

Страница 22: ...steps are as follows If no change is desired at any step within process simply depress the PROG to advance through the program cycle Once all four Set Points and four settings per set point are compl...

Страница 23: ...ressure Be sure all piping is supported Filters should be piped in accordance with the instruction tags flow arrows and IN and OUT labels supplied with the filter See recommended system installation d...

Страница 24: ...rt of the filtration system The liquids that accumulate here must be drained at regular intervals in order to prevent the condensate from being re in trained in the filtered air A typical drain system...

Страница 25: ...liminates time and travel by a service company making one trip with parts in hand It helps us to determine situations non related to the dryer After the phone call has been placed and if service is ne...

Страница 26: ...le of 1 being the lowest to 5 being the highest Condition of Arrival Ease of Installation Ease of Start Up Product Quality Technical Assistance Clarity of Instruction Warranty Manual FINAL OPERATION C...

Страница 27: ...27 DTX10 DTX80 USER GUIDE Appendix Spare Parts...

Страница 28: ...28 DTX10 DTX80 USER GUIDE Appendix Drawings...

Страница 29: ...any 49 0 711 7071 290 10 www parker com rfde Hydraulic Filtration Hydraulic Filter Arnhem Holland 31 26 3760376 www parker com hfde Urjala Operation Urjala Finland 358 20 753 2500 www parker com hfde...

Отзывы: