Polar Bear III HD Mechanical Attachment Bracket Installation Manual
9910031 Rev F
13
10 Degree South Support Mechanical Attachment location and
Mechanical Attachment Installation
Step 1: Position the Mechanical Attachment
1.
Consult the provided Racking Construction Set Drawing for the locations of the Mechanical
Attachments that need to be installed. Once the module and Supports are installed you can
locate the Mechanical Attachment. Ballast Trays will need to be removed if they are already
installed.
2.
The Mechanical Attachments are installed between two adjacent south supports and connect to
the center of the Ballast Trays.
3.
Place the Mechanical Attachments matching the hole location in the Ballast Tray.
Notes:
Drill a ½” hole in the middle of the Ballast Tray if needed.
Figure 11 Place the Mechanical Attachment underneath the center of the Ballast Tray
South Supports
Match the Mechanical
Attachment to the hole
in the Ballast Tray
Mechanical Attachments are installed
between two adjacent South Supports