Hand Over to Customer
PACD011001G2 / PACD011004G3
70
Urban Multi Inverter “MX1” Series
6.
Hand Over to Customer
6.1
Operational Steps
Important Points
a) The measurements taken during the test run should be recorded and kept on a test run inspection
sheet.
b) Do not forget to record the length of the refrigerant piping and the refrigerant additional charging
volume on the plate on the back of the outdoor unit external notice board, as this information will be
required for servicing the system.
c) Explain to the customer how to operate the equipment and let him try it.
d) Assemble all the relevant diagrams and other printed matter which is required to operate the system
and hand it all over to the customer (on the spot) and tell him to keep it.
e) Make the service contact address clear.
Complete test run
Make final report
(test run
inspection sheet)
Explain how to
operate
equipment
Hand over
relevant printed
materials
(V1050)
Содержание Urban Multi MX1 Series
Страница 34: ...Installation 1 PACD011001G2 PACD011004G3 34 Urban Multi Inverter MX1 Series Ceiling Type CS TM ...
Страница 54: ...Installation 1 PACD011001G2 PACD011004G3 54 Urban Multi Inverter MX1 Series ...
Страница 102: ...Appendix Check Points in Installing UM Series PACD011001G2 PACD011004G3 102 Urban Multi Inverter MX1 Series ...
Страница 103: ...PACD011001G2 PACD011004G3 Appendix Check Points in Installing UM Series Urban Multi Inverter MX1 Series 103 1 ...
Страница 104: ...Appendix Check Points in Installing UM Series PACD011001G2 PACD011004G3 104 Urban Multi Inverter MX1 Series ...