10. Finish ceiling work.
A circle ceiling hole ( 6 1/2 inches (165mm) dia.)
should be cut. And make sure there will be
a gap ( >1/8 inches (3.2mm )) between bottom of
fan body and ceiling. (Fig. 7)
12. Install the supplied LED lamp. (Fig. 9)
11. Unlock the lamp cover.(Fig.8)
LIGHTING UNIT POSITION
Do the following to adjust the lighting unit:
Lighting unit
(Push the
lighting unit
vertically)
Blower unit
Down
Up
(Rotate the lighting unit)
2
1
The lighting unit position is adjustable in the range of
1/2 inches (12.7mm). The “Up” position (the factory
setting) is recommended for normal installation.
In case of Furring Strap Joist installation, the “Down”
position is acceptable.
Fan body
Lighting unit
Ceiling
Joist
Down
Up
The “ “ arrow point to “Up”
Lighting unit
Fan body
Ceiling
Furring
Strap
Joist
Down
Up
The “ “ arrow point to “Down”
Down
Up
6 1/2 (165) Dia.
lamp cover
Ceiling
Ceiling
hole
Fig. 7
Ceiling
Suspension
bracket
Joist
>1/8 (3.2)
After finishing the ceiling job, fill gap
between flange and ceiling with caulk
or other sealant to prevent air leakage.
Fig. 8
Lamp cover
Down
Up
Failure to follow the above method may
result in poor performance.
Use other lamp may result in poor performance
or risk of fire.
Down
Up
Fig. 9
LED lamp
8
INSTALLATION (BETWEEN JOISTS MOUNTING) CONTINUED
The supplied LED lamp is not intended for
other use.