Installation Sequence
Use the following guidelines to help ensure a smooth and error-free installation. The installation sequence is
divided into three phases: planning, installation, and startup.
First Trip to Site: Planning Phase
Consult with the contractor and go over all ORTAL requirements:
x
Chase and framing requirements
x
Drywall or noncombustible inside the chase
x
Air intake and heat release
x
Access panel size and location
x
Gas and electric specs and location
x
Flueing configuration
x
Finishing details
Second Trip to Site: Installation Phase
x
Confirm the framing and platform are built to spec.
x
Confirm gas valve is in the correct location.
x
Confirm access panel location and size.
x
Confirm air intake and heat release locations.
x
Make sure there is a clear path to carry in the unit.
x
Uncrate the unit and set in place.
x
Use the shipping bracket for the legs and seismic brackets to level and secure the unit (see note
below).
x
Cut off ALL the zip ties.
x
Move the components to the access panel location. Be mindful of the routing for future service needs.
x
Install the flueing components per the flueing
manufacturer’s instructions and ORTAL requirements.
x
Go over the infill panel requirements and finishing details with the contractor.
x
Protect the fireplace and components from damage.
SECURING THE UNIT: Use the supplied seismic brackets and leg shipping brackets to secure and level the
fireplace. If necessary, the brackets can be extended with similar steel components.
It is crucial to the finishing that the unit is stable, level and plumb. The legs are zero clearance. Wood shims are
acceptable.
Third Trip to Site: Startup Phase
x
Perform a visual inspection to confirm that all work was completed per ORTAL specifications.
x
Confirm that gas is properly connected and live.
x
Remove the safety barrier and glass.
x
Clean the inside of the unit.
x
Confirm operation and remote control setup.
x
Set up the media per ORTAL specifications.
Содержание Clear 200
Страница 1: ...Installation and Operation Manual AU NZ For 150 250 Units ORTAL Heating Systems Ltd ...
Страница 17: ...17 LEFT SIDE OPEN LS RIGHT SIDE OPEN RS THREE SIDES TS ...
Страница 21: ...21 Figure 3 Concrete Wall Mounting Detail ...
Страница 23: ...23 Figure 4 Wood Stud Mounting Detail ...
Страница 43: ...43 Figure 12 Exploded View of Pilot Parts Receiver and Gas Valve ...
Страница 55: ...55 Figure 12 Exploded View of Pilot Parts Receiver and Gas Valve ...
Страница 77: ...77 Flue Termination Drawings Flue Terminations ...
Страница 89: ...89 Pull the suction cup to take the glass out NOTE Repeat this process to remove the side glass ...
Страница 102: ...102 Pull the framed screen down and out and remove it ...
Страница 120: ...120 6 Push the right and left floor bricks into place as shown ...
Страница 125: ...125 ...
Страница 135: ...135 ORTAL Product Service Log ...
Страница 136: ...136 Manufacturer Contact Information For all service issues please contact your local dealer ...
Страница 146: ...146 Troubleshooting Beeping ...
Страница 147: ...147 ...
Страница 148: ...148 Mertix Maxitrol External Source Operation The following figure is taken from the Mertix Maxitrol guide ...
Страница 154: ...154 Pull the base until it releases Tilt the base as shown in the figure below ...
Страница 155: ...155 Pull the base out as shown ...
Страница 156: ... Ortal 2018 Rev 3 0 October 2018 KPMANUALAUAGA ...