IG-308-EN version 01; 03/06/2022
47
General instructions
cgm
.3-huv system: Fully gas-insulated
medium-voltage switchgear
Recommended sequence of operations
5.5.6. Earthing operation from isolating position
Initial conditions:
circuit-breaker open, earthing
switch open and springs charged.
1.
Close the circuit-breaker by pressing the "l" close button
and check the status indicating relay.
Figure 5.32.
Closing button detail
2.
Check that no voltage is present through the
ekor
.vpis
unit.
3.
Move the access handle in the yellow zone to its bottom
position.
Figure 5.33.
Handle detail