IG-308-EN version 01; 03/06/2022
21
General instructions
cgm
.3-huv system: Fully gas-insulated
medium-voltage switchgear
Installation
4.5. Fixing to floor
[8]
See section 5. Operations Sequence
Before assembling the cubicles, the floor must be carefully
levelled to prevent any deformation which may make it
difficult to connect the cubicles to one another.
The cubicles can be fastened to the floor in two ways:
4.5.1. Fixing to floor on profile
If the floor of the facility is not sufficiently uniform, it is
advisable to install the medium-voltage cubicles on an
auxiliary profile, to make it easier to connect. This profile,
which can be supplied to order, must be anchored to the
floor using expansion bolts.
a
M10 x 25 bolt
b
65 x 65 x 4 mm profile
c
Anchoring bracket
Figure 4.6.
Positioning cubicles on profile
4.5.2. Fixing to floor by anchoring
If the floor of the facility is level enough, it is advisable to
install the medium-voltage cubicle anchored directly to the
floor.
The sequence for fixing the cubicles to the floor is as follows:
1.
The cubicle's switch must be in earthing position
[8]
.
By default, the cubicles are supplied with the switch in
earthing position. Except in circuit-breaker functions,
which will be in isolating position.