10. Lower cabinet over rod and level as needed.
11. Place anchor stack-up parts on rod (see
Figure 24: Raised Floor Anchor
a) Plate washer
b) Fiber washer
c) Bushing
d) Large washer
e) Flat washer
12. Re-thread torque nut onto rod.
13. Tighten torque nut until it separated, approximately 60 ft. lbs.
Procedure — Raised Floor Earthquake Bracing
This section describes how to install earthquake bracing to a raised floor installation. Bracing is required
in earthquake zones 3 and 4 when installing a cabinet onto a raised floor with a spacing of 1.5 feet or
more between the raised floor and the subfloor
1. Assemble the Earthquake Brace by securing the 45 degree bar steel pieces to the flat 90 degree bar.
Use the Earthquake Brace Kit.
Figure 25: Earthquake Bracing
2. On the threaded rod located at the front of the cabinet:
a) Install a 5/8" nut onto the rod. The nut will need to be threaded approximately 5 inches from
the top of the raised floor.
b) Place a helical washer onto the rod.
c) Place a flat washer onto the rod.
3. On the threaded rod located at the back of the cabinet, place a flat washer on the threaded rod so
that the washer is sitting on the nut holding the anchor in place.
4. Place a flat washer on the back threaded rod.
5. Slide the Earthquake brace onto the threaded rod from the front threaded rod to the back threaded
Note: Do not over adjust as this may cause the tile or cabinet to tilt.
53
910-5681-001 Revision E, February 2014
Cabinet Installation
Installation