Procedure — Optional Hoist with Crane
Another option to unpack the cabinet is to remove the cabinet from the pallet and lower it to the floor
using hoisting eyebolts and a crane. Use this method if there is not enough room to open the crate and
use the door ramp.
Warning: To avoid physical injury, be sure that properly rated hoisting equipment is
used. When hoisting the cabinet, pull straight up slowly on the eyebolts using properly
rated hardware attached evenly to the eyebolts to prevent the cabinet from swinging.
Always secure the cabinet during lifting to minimize swing.
1. Remove crate lid.
2. Screw the eyebolts completely into the top of the cabinet.
3. Securely attach the eyebolts to a hoist. The hoist should be positioned so that the four eyebolts
evenly support the weight of the cabinet.
4. Use the 15/16” socket wrench with 15/16” drive ratchet to unbolt the cabinet from the crate.
5. Using a crane, carefully lift the cabinet off the pallet and lower the cabinet into its final position
over the anchor holes drilled in the floor.
Minor manual adjustments may be necessary to ensure correct alignment of the cabinet to anchor
sites.
Installing the Cabinet
You must bolt the seismic cabinet to a floor using the anchors provided. The following steps are
required to install the cabinet.
•
Procedure — How to Mark the Floor Layout
•
Procedure — Prepare Raised Floor for Anchors
•
•
•
Procedure — Raised Floor Earthquake Bracing
•
Procedure — Anchor Cabinet on Concrete Floor
• Install kick plates (see
) with 10 mm allen wrench
47
910-5681-001 Revision E, February 2014
Cabinet Installation
Installation