Overview
This chapter describes how to unpack the application cabinet from the crate, prepare a concrete or
raised floor for installation, anchor the frame to floor and overhead rack, examine the grounding
requirements and the cabling.
Unpacking the Cabinet
This section describes the steps to unpack the cabinet. Each cabinet is shipped in a wooden crate on
a shock pallet. See
Figure 17: Packed Cabinet Crate
Figure 17: Packed Cabinet Crate
Required Tools
• 9/16” Open End Wrench
• 9/16” Socket with Drive Ratchet
• 15/16” Socket with 1/2” Drive Ratchet
• 15/16” Open End Wrench
• 10 mm Allen Wrench
• 19 mm Socket with Drive Ratchet
43
910-5681-001 Revision E, February 2014
Cabinet Installation
Installation