Reliable earthing of rackmounted equipment should be maintained. Particular
attention should be given to supply connections other than direct connections to
the branch circuit (for example, use of power strips).
•
Slide-rail mounted equipment must not be used as a shelf or a work space.
3.4 Disassembling the Slide-Rails
To disassemble the slide-rails before the installation, complete the following steps:
1.
Unpack the slide-rails.
2.
Locate the slide-rail lock at the front of the slide-rail assembly, as shown in
.
3.
Press and hold the slide-rail lock toward the direction of the arrow, while you pull
the mounting bracket out of the slide-rail assembly until it reaches the stop, as
shown in
4.
Push the mounting bracket release button toward the front of the mounting bracket
(
), and simultaneously withdraw the mounting bracket from the slide-rail
assembly.
Figure 3-1 Disassembling the Slide-Rails Before Installation
Table 3-2 Figure Legend
Number
Description
1
Slide-rail lock
2
Mounting bracket release button
3.5 Installing the Mounting Brackets Onto Oracle Exalytics
In-Memory Machine
You must install the mounting brackets onto the Oracle Exalytics In-Memory Machine
before you can rackmount it.
To install the mounting brackets, complete the following steps:
1.
Position a mounting bracket against the chassis so that the slide-rail lock is at the
Oracle Exalytics In-Memory Machine front, and the five keyhole openings on the
Chapter 3
Disassembling the Slide-Rails
3-3