Delivery
INFORMATION
The machine is pre assembled. It is delivered in a transport box. After the unpacking and the
transportation to the installation site it is necessary to mount and assemble the individual
components of the machine.
Check the status of the machine immediately upon receipt and claim possible damages at the
last carrier also if the packing is not being damaged. In order to ensure claims towards the
freight carrier we recommend you to leave the machines, devices and packing material for the
time being in the status at which you have determined the damage or to take photos of this
status. Please inform us about any other claims within six days after receipt of delivery.
Check if all parts are firmly seated.
3.2.1
Load suspension point
DANGER!
Danger of crushing and overturning. The lathe must be installed by several persons.
Check the horizontal orientation of the base of the lathe with a spirit level.
Check that the foundation has sufficient load-bearing capacity and rigidity.
Anchor the machine base or the optional machine base onto the floor before positioning the
machine on it.
Make sure that a sufficiently stable lifting sling (tape sling) is used that can bear the weight.
Place the lifting sling around the spindle behind the lathe chuck (2) and then around a rib
(4) of the machine bed. Then hook the end of the sling back into the crane hook (5). Push
the tailstock as far forward as possible. Pay attention to the load centre of gravity, if
necessary adjust the position of the sling in the crane hook (3).
Raise the lathe only as far as is necessary to carry out the work.