3. Connecting load
ATTENTION
The UPS system has two groups of output sockets. Critical load should not be connected to the
programmable output sockets. To connect the load to the UPS system, use the cold device extension
cables provided.
4. Connecting battery pack
To connect additional battery packs, connect their “VDC Output” to the “VDC Input” of the upstream
battery pack. The battery pack connected directly to the UPS system is connected to the “VDC Input” on
the UPS system. Switch on the battery fuse on the back of the battery pack. Enter the number of
battery packs used in menu no. 7 (see manual).
5. Supply the UPS system with utility power
Plug the mains connection cable of the load into a wall outlet socket. For the
2000VA and 3000VA models, a 16A mains connection cable is also supplied.
The display on the UPS system shows “Sb”.
6. Switching on the UPS system
Hold the “ON / / ” button on the UPS system down until you hear a short
beep. The UPS system carries out a self-test, after which “OK” appears on the
display and continues in normal mode.
7. If an additional emergency stop switch has been installed, the emergency stop function needs to be tested.
8. Switch the load on one by one.
The comprehensive user manual is available to download free at
Safety information and quick start guide UPS XANTO
•
Page 10