7-10 Performing Safety Validation and Op-
eration
This section describes the procedure for safety validation testing. Safety validation testing is used to
confirm that all safety functions and all Safety Control Units meet the required specifications of the
safety system. If safety validation testing demonstrates that the safety controls meet the required
specifications of a safety system, the safety application data is appended with confirmation information
through a process called "safety validation".
When you perform safety validation on a Safety CPU Unit that is operating in DEBUG mode, the safe-
ty application data is saved in the non-volatile memory of the Safety CPU Unit.
This section describes how to perform safety validation and start operation after you have debugged
the safety programs.
7-10-1
Performing Safety Validation
You must perform safety validation before you change Safety CPU Unit to the RUN mode and start
any safety control system that uses safety application data
*1
that is created with Sysmac Studio.
You perform safety validation after you perform safety validation testing with the Safety CPU Unit in
DEBUG mode (RUN) to make sure that all safety functions operate as intended.
To perform safety validation, it is necessary that the Safety CPU Unit be in DEBUG mode.
*1. The safety application data includes the safety programs and the safety task settings and variables. Refer to
7-1 Procedures before Operation and Transferring the Required Data
WARNING
Before you perform safety validation of the safety programs, complete
debugging of the safety programs.
Otherwise, the Safety CPU Unit will start with safety programs that are
not fully debugged and may cause serious personal injury.
WARNING
Verify the calculated reaction times for all safety chains to confirm that
they satisfy the required specifications.
Serious injury may possibly occur due to loss of required safety func-
tions.
Additional Information
You can manage changes in the safety application data before you perform safety validation af-
ter debugging is completed, or after you perform safety validation. Refer to
on page A - 70 for details.
l
Performing Safety Validation
7 Checking Operation and Actual Operation
7 - 56
NX-series Safety Control Unit User's Manual (Z930)
Содержание NX-SIH400
Страница 4: ...Introduction 2 NX series Safety Control Unit User s Manual Z930 ...
Страница 46: ...Revision History 44 NX series Safety Control Unit User s Manual Z930 ...
Страница 108: ...2 Specifications 2 42 NX series Safety Control Unit User s Manual Z930 ...
Страница 132: ...3 Installation and Wiring 3 24 NX series Safety Control Unit User s Manual Z930 ...
Страница 148: ...4 Safety Control Unit Operation 4 16 NX series Safety Control Unit User s Manual Z930 ...
Страница 216: ...5 System Configuration and Setup 5 44 NX series Safety Control Unit User s Manual Z930 ...
Страница 306: ...6 Programming 6 90 NX series Safety Control Unit User s Manual Z930 ...
Страница 378: ...7 Checking Operation and Actual Operation 7 72 NX series Safety Control Unit User s Manual Z930 ...
Страница 390: ...8 Calculating Safety Reaction Times 8 12 NX series Safety Control Unit User s Manual Z930 ...
Страница 412: ...11 Safety Data Logging 11 10 NX series Safety Control Unit User s Manual Z930 ...
Страница 504: ...12 Troubleshooting 12 92 NX series Safety Control Unit User s Manual Z930 ...
Страница 550: ...l Safety I O Terminal Settings l I O Map Settings Appendices A 38 NX series Safety Control Unit User s Manual Z930 ...
Страница 554: ...l I O Map Settings Appendices A 42 NX series Safety Control Unit User s Manual Z930 ...
Страница 558: ...l Safety I O Terminal Settings l I O Map Settings Appendices A 46 NX series Safety Control Unit User s Manual Z930 ...
Страница 564: ...l Safety I O Terminal Settings l I O Map Settings Appendices A 52 NX series Safety Control Unit User s Manual Z930 ...
Страница 623: ...I Index I 1 NX series Safety Control Unit User s Manual Z930 I ...
Страница 625: ......