Solarion
M210P
EN V1.0 2015-10-20 © OC3 AG
Figure 1: Correct module orientation
A qualified installer should provide to you a plan of your solar system, including module layout, string plan and electrical plan.
Shading of the solar system at times of high irradiation, particularly between the hours of 9:00 and 15:00, should be avoided. It is
recommended that a professional installer investigate possible shading instances at all times of the year (e.g. with the aid of a SunEye)
prior to module installation.
The Solarion
M210
module is appropriate for flat-roof and low-slope systems with a tilt angle between 3° and 10° .
The likelihood for ponded water is higher on rooftops below 3°, and the possibility for heavy snow loads to place significant stress on the
module junction boxes and cables is high on rooftops above 10°. Where installation sites receive no snowfall or ice build-up, mechanical
fastening of the module must be used on rooftop pitches greater than 40°. Please consult with your roofing specialist or installer.
All mounting components used with the Solarion M2
1
0 modules must be UL-listed and/or IEC certified and must meet the applicable Code
requirements.
It must be ensured that the intended installation site has adequate drainage and experiences no standing water, even after heavy rainfall.
If the modules are not mounted onto a verifiable positive drainage surface according to the presiding roofing codes
at the site of installation, the warranty of the product will be voided. It is also vital to ensure that the upper edges of the
module be suitably protected against snow and ice run-off when installed on pitched rooftops.
Solarion solar modules are guaranteed to support a maximum snow load of 2.4 kPa (2400 N/m
2
) only when the module is installed on to
roofing membrane or other membrane surface with membrane welding on all 4 edges of solar panel considering backsheet type of solar
module and designated installation surface made from same material. For example if you are going to install this solar panel on to
TPO based membrane, then you should install Solarion
M210P
PVC
modules. If you wish to use a special mounting system that
is not approved for use by Solarion, you must first obtain written permission by OC3 AG, otherwise the guarantee
will be voided.
!
"
Water
Drain