Installation Manual

Ducting For Wall Mounted ECO4 MVHR Units

3.2 Final Installation

The MRXBOX-FF4 should be secured to the slab/joists/ceiling using 
appropriate fixings (supplied by others), it should be aligned centrally in 
both axes (Figure 2) to the corresponding MVHR unit being connected 
to minimise misalignment between the ducts.  

Appropriate ducting should then be used to connect the  
MRXBOX-FF4 to MRXBOXAB-ECO4 or ancillary MRXBOX-SIL4 if used, 
suitable clearance should be allowed around any connecting ducting 
passing through the ceiling to prevent vibration being transferred to the 
building structure.

MRXBOX-FF4 Ducting View

SECTION 1. First Fix Plenum Chamber (Code:MRXBOX-FF4) 

Rectangular spigots 220 x 90mm.

4 Hanging brackets

Ducting (by others). 

Rectangular spigots 220 x 90mm.

Hanging brackets fix to the underside
of the floor slab at first fix stage of 
the build.

Optional Ancillary Item MRXBOX-AV4 
Sold Separately (Must Be Used If Also 
Fitting MRXBOX-SIL4)

SECTION 3. MRXBOXAB-ECO4 MVHR Unit 

DUCTING

MRXBOX-FF4 ALIGNED CENTRALLY IN
BOTH AXES TO THE MRXBOXAB-ECO4

SLAB / JOIST / CEILING

FRONT VIEW

SIDE VIEW