Novatek-electro RN-16TM Скачать руководство пользователя страница 6

- 6 - 

RN-16TМ 

                                                                                               

NOVATEK-ELECTRO

 

               - illumination level threshold setting. 

Important notes: 
Quality of the mains voltage power supply doesn’t influence on the preprogrammed 

operation schedule of the RN-16TM. So after the normalization of the voltage parameters 
power load will be turned ON again, but according to the time schedule preset by the user. 

If mains voltage was absent not more than 1 month (device was disconnected for 30 

days) all the parameters and settings will be safely kept in the RN-16TM memory. Output 
contacts of the relay will be kept in a cold initial state. 

For example RN-16TM was preprogrammed such a way that every day of a week it 

turn  ON  the power load at 22:00 and then at 8:00 in the morning of next day it turns the 
power load OFF. Let’s assume that at 22:30 on Monday mains voltage disappeared and 
then recovered back only on Wednesday at 6:00 in the morning. So when voltage 
disappeared contacts 3-4 opened.  

As soon as the power load restore and return back to normal values RN-16TM will turn 

ON the power load again but according to the preprogrammed schedule of operation. So at 
6:00 when the power return – it will turn ON the power load and at 8:00 in the morning that 
will turn it OFF according the schedule. 

 

4 FIRST STARTUP PROCEDURES AND OPERATION ALGORHYTM 

 

For preservation of working capacity of an inner clock when disappearance of 

voltage

, it is necessary to establish a strap 5-6 

(Figure

 1). 

Preliminary start up procedures include the following steps:  

 setting of the current time and the day of a week; 

 setting the schedule of events (exact time values and days of a week when 

the power load should be turned 

ON

 and turned 

OFF

 as per users requirements); 

 setting the voltage tripping thresholds for MIN/MAX allowed voltage values 

 setting the delay times to turn 

ON

 for UPPER/LOWER voltage thresholds  

 setting the autoreclosing time delay 

 setting the level of illumination (if necessary) 

If in the menu some parameter or event is seen blank (“_”) then the event or parameter 

in not set. 

When setting the time event schedule it’s possible to adjust the following parameters: 

 

          - turn 

ON

 time;              - turn 

OFF

 time;               - current time 

where: “01” – is number of event (

ON/OFF

);  

x  –  days of a week, it’s possible to set 1-7 values (Monday –  1; Tuesday –  2; 

Wednesday – 3; Thursday – 4; Friday – 5; Saturday – 6; Sunday – 7); 

A – equal time-schedule for all days of a week; 
B – equal time-schedule for working days (Monday-Friday); 
C – equal time-schedule events for weekend days (Saturday-Sunday); 

 

To give the power supply to the RN-16TM it’s necessary to connect mains voltage 

wires to 1-1 and 2-2 input contact terminals. 

 

ATTENTION! All connections of terminals should be performed strictly according 

to safety regulations and in the absence of voltage in the mains. So before wiring 
make sure that the wire terminals are not under voltage. 

 

Н_ _ _

    

Е01.х

 

d

01.х

 

L_ _ 

 

 

CLOC 

Содержание RN-16TM

Страница 1: ...NOVATEK ELECTRO LTD Research and Manufacture Company RN 16TM LIGHT SENSITIVE MULTIFUNCTIONAL DAILY WEEKLY TIMER SERVICE MANUAL www novatek electro in...

Страница 2: ...t hours blinking point minutes 16 hours 45 minutes II Mode U present voltage level correct to the nearest tenth 221 5 Volts III Mode F letter F space illumination level illumination level 35 IV Mode H...

Страница 3: ...nu parameter input save the parameter and menu exit scrolling buttons 5 8 wiring terminals 6 seven segment indicator display 7 green LEDs to indicate the operation mode of the relay 9 strap of interna...

Страница 4: ...er load 16 no less than operations under load 5A no less than operations 100 000 1 000 000 Power consumption under load VA not more than 3 0 Weight not more than kg 0 150 Dimensions mm 50 88 65 Operat...

Страница 5: ...the operation mode F U H of the RN 16TM to set the operation mode and curtain user required set of parameters there are 2 independent sets of parameters programs that the user may keep in the device...

Страница 6: ...rking capacity of an inner clock when disappearance of voltage it is necessary to establish a strap 5 6 Figure 1 Preliminary start up procedures include the following steps setting of the current time...

Страница 7: ...ut contacts of RN 16TM ATTENTION In order to prevent possible electric shock all the connections of the power load should be performed according safety regulations and on the de energized RN 16TM To p...

Страница 8: ...ss and while keeping button pressed set the required lower voltage threshold then release the button when the setting is done blinking dot Set lower voltage threshold value in the range 150 210 blinki...

Страница 9: ...e in the device memory Save and Exit 14 Select dL 90 item blinking dot turn OFF time delay in case undervoltage detected 15 Press and while keeping button pressed set the required value then release t...

Страница 10: ...orresponds to current hour 6 Press and set the current hours blinking hours position Set the value from 0 to 9 to that corresponds to current hour 1 5 _ _ 7 Press and set current minutes 1 5 _ _ blink...

Страница 11: ...ind F PA mode 3 Press and while keeping button pressed set the required value then release the button when the setting is done blinking dot Set the value in the range 0 175 blinking dot 4 Press calibr...

Страница 12: ...ress and Exit the menu 8 TO DELETE CURRENT SET OF ADJUSTMENTS 1 Perform steps 1 2 of the section 7 2 Press and while keeping button pressed delete the settings then release the button blinking dot Pre...

Страница 13: ...KW THE RELAY MAY OPERATE WITH THE LOAD DIRECTLY VARIANT B IF THE POWER LOAD IS MORE THEN 16A 3 5 KW THE RELAY MUST OPERATE WITH THE POWER LOAD USING THE ADDITIONAL MAGNETIC CONTACTOR THAT WILL COMMUT...

Страница 14: ...ackage and the RN 16TM material The Buyer must provide the protection of the timer against mechanical damages in transit 7 WARRANTY AND CLAIMS CONDITIONS Novatek Electro Ltd company warrants a trouble...

Отзывы: