5.5 COMMUNICATION CONNECTION(S)

For UTP connection (preferred) proceed with 5.5a,  
for GPRS connection proceed with 5.5b;  
(refer to 3.4 & 3.5 Product Overview)

5.5A COMMUNICATION CONNECTION(S) (UTP)

Step 1; Feed the UTP cable(s) through the rubber 
stop(s) on the data cable inlet and then connect it to 
the Ethernet port(s), like indicated in the ‘overview of 
connections’ section;
Step 2; Connect the UTP to an internet enabled router 
with DHCP;

5.5B COMMUNICATION CONNECTION(S) 

(GPRS)

 

Step 1; Check and make sure signal strength  
is sufficient;

5.6 OPTIONAL DPM (PURCHASED 

SEPERATLY )

Step 1; Make sure to follow the DPM installation manual 
in conjunction with this manual.
Step 2; Check if the Phase 1 in chargepoint match the 
Phase 1 of the DPM device. If not, correct that first.
Step 3; Feed the UTP cable through the rubber stops on 
the data cable inlet and then connect the RJ12 (6P6C) 
connector
to the P1 port. Connectors on this cable should be 
straight, which means the same order on both sides of 
the cable.
Step 4;  Contact New Motion after step 5.7 for activation.

5.7 FINISHING UP (CLOSE ENCLOSURE)

Step 1; Check and make sure that the rubber enclosure 
seal is properly in place on the enclosure edge all 
around;
Step 2; Place the enclosure cover on the charge point;
Step 3; Hand-tighten the four M4 x 12mm bolts provided 
around the socket so that the cover closes on the rubber 
seal but the rubber seal does not deform;
Step 4; Hand-tighten the other two M4 x 12 mm bolts 
provided in the bottom of the cover;
Step 5; Turn the socket lid or dummy socket clockwise 
in the cover and hand-tighten the M4 x 20mm bolt 
provided;
Step 6; Switch on power to the charge point;
Step 7; Wait until charge point is fully started up (+/-10 

minutes, LED should be off);
Step 8; Check that the charge point is connected to the 
network. A quick check can be done via chargeportal.
newmotion.com/test. Simply enter the serial number 
into the search field and click “Search”. “Online” should 
appear after the serial number. If “Online” does not 
appear, check whether the charge point is properly 
connected and try again. For persistent issues, please 
contact NewMotion. 
Step 9; If configuration of the charge point power 
settings is needed (for example lower Amp settings) 
please contact NewMotion;

5.8 CHECK FUNCTIONING

Step 1; Power on the chargepoint and let it start up (give 
it a few minutes);
Step 2; Check start screen and connection, the display 
should show the initial start screen as shown below;
Step 3; The date and time need to show up as grey 
text. If it shows red text the SMED is not synchronised 
(backoffice connection issue) or not yet fully started up;
Step 4; You can refer to the user manual for more use 
related instructions*;
*Alternatively the owner/operator manual can also be 
consulted.

5. INSTALLATION PROCEDURE

Содержание Home Advanced View

Страница 1: ...INSTALLATION MANUAL Home Advanced View 3 7 22 kW INSTRUCTION MANUAL EN INSTALLATIONSANLEITUNG DE VERSION 075NM19INT01...

Страница 2: ......

Страница 3: ...NewMotion Home Advanced View 3 7 22 kW Table of contents Inhaltsverzeichnis DE 49 0 30 215 028 48 Instruction manual EN Pages 4 16 Installationsanleitung DE Pagina 17 30...

Страница 4: ...y guidelines are intended to ensure correct in stallation and usage Any failure to comply with the valid safety guidelines or instructions provided in this manual may result in fire electrocution or s...

Страница 5: ...eady for use the owner needs to activate the charge point through our online portal at my newmotion com The serial number of the charge point is needed for this process which can be found on the right...

Страница 6: ...ure Spirit level All mentioned for standard mounting plus Pole sold separately 4 x M8 wedge bolts or chemical anchors plus nuts and washers All mentioned for pole mounting plus Concrete base sold sepa...

Страница 7: ...tness IEC 60529 IP code protection class EN 50470 M class EN 50470 E class Certificates kWh measurement User interface 07 5 _ _ _ _ _ 1 phase 32A 7 4 kW 3 phase 32A 22 kW 1 phase 16A 3 7kW 3 phase 16A...

Страница 8: ...otective Earth connection Class I 3 2 TECHNICAL SPECIFICATIONS 3 PRODUCT OVERVIEW Identification Communication backoffice Communication Smart Meter Backoffice protocol Stand by consumption Operating t...

Страница 9: ...INSTALLATIEHANDLEIDING P9 VERSION 0129NM02INT01 INSTRUCTION MANUAL P9 P9 075NM19INT01 EN DE 3 PRODUCT OVERVIEW 3 3 OVERVIEW OF PRODUCT...

Страница 10: ...1 phase and connect one of the two other phase wires in the neutral wire connection on the terminal block INSIDE RJ45 Ethernet port RJ12 P1 port DPM UTP data cable inlet with rubber seal Inlet for pow...

Страница 11: ...t with rubber seal UTP data cable inlet with rubber seal Inlet for power cable with tension relief clamps Terminal block DC protection module Connection DC protection module Tension relief for data ca...

Страница 12: ...r online services can be used 3 5 1 HOME ADVANCED VIEW ETHERNET NEWMOTION MOBILE ROUTER Connecting the Home Advanced View to an ethernet or mobile router can be done by connecting the network to the l...

Страница 13: ...uation and according to regulations The electrician is always responsible for selecting a cable thickness appropriate for the specific situation and according to regulations 3 phase charge point can a...

Страница 14: ...attachment points Ensure that the grey spacers are placed on the back of the charge point at the bottom two attachment points 5 2B MECHANICAL MOUNT POLE ON PAVEMENT Step 1 Drill holes into the pavemen...

Страница 15: ...charge point Step 3 Hand tighten the four M4 x 12mm bolts provided around the socket so that the cover closes on the rubber seal but the rubber seal does not deform Step 4 Hand tighten the other two M...

Страница 16: ...ge point by plugging in the charge cable If you are using Plug Charge the session will start automatically If you have to identify first swipe your charge card above the LED The LED will flash green t...

Страница 17: ...ng gew hrleisten Die Nichteinhaltung der Richtlinien und Anweisungen in diesem Handbuch kann zum Brand Stromschlag oder zu schweren Verletzungen f hren Die Ladestation ist ein Produkt der Schutzklasse...

Страница 18: ...satz vorzubereiten muss der Eigent mer die Ladestation ber unser Online Portal my newmotion com aktivieren Die Seriennummer der Ladestation wird in diesem Prozess ben tigt und kann auf der rechten Sei...

Страница 19: ...plus Mast separat erh ltlich 4 M8 Keilbolzen oder Verbundanker plus Muttern und Unterlegscheiben Alle f r die Mastbefestigung erw hnten Elemente plus Betonsockel separat erh ltlich DIN 912 HEX Inbussc...

Страница 20: ...Code Schutzklasse EN 50470 M klasse EN 50470 E klasse Zertifikate kWh Messung Benutzeroberfl che 07 5 _ _ _ _ _ 1 phasig 32 A 7 4 kW 3 phasig 32 A 22 kW 1 phasig 16 A 3 7 kW 3 phasig 16 A 11 kW Klass...

Страница 21: ...e Klasse II Montage am Metallmast mit Schutzleiteranschluss Klasse I 3 2 TECHNISCHE DATEN 3 PRODUKT BERSICHT Identifizierung Backoffice Kommunikation Kommunikations Smart Meter Backoffice Protokoll St...

Страница 22: ...INSTALLATIEHANDLEIDING P22 VERSION 0129NM02INT01 INSTALLATIONSANLEITUNG P22 P22 075NM19INT01 EN DE 3 3 BERSICHT BER DAS PRODUKT 3 PRODUKT BERSICHT...

Страница 23: ...er aufbauen Installieren Sie nur die Phase 1 und verbinden Sie einen der beiden anderen Phasendr hte mit dem Nullleiter Anschluss INSIDE RJ45 Ethernet Anschluss RJ12 P1 port DPM Einlass f r UTP Datenk...

Страница 24: ...TP Datenkabel mit Gummidichtung Kabeldurchf hrung festes Ladekabel Klemmblock DC Schutzmodul Anschluss DC Schutzmodul Zugentlastung f r Datenkabel L1 N PE Erdung Erdungspfosten Phase 2 Phase 3 3 PRODU...

Страница 25: ...ME ADVANCED VIEW ETHERNET NEWMOTION MOBILROUTER Die Verbindung von Home Advanced View zum Ethernet oder Mobilrouter kann hergestellt werden indem das Netzwerk ber ein max 50 Meter langes Kabel an den...

Страница 26: ...antwortlich Der Elektriker ist f r die Auswahl einer f r die spezifische Situation und die gesetzlichen Bestimmungen geeigneten Kabeldicke verantwortlich Die 3 phasige Ladestation kann auch 1 phasig a...

Страница 27: ...er Schrauben Unterlegscheiben Schritt 3 Sichern Sie die Ladestation an der Wandhalterung mit den mitgelieferten zwei M8 x 12 mm Schrauben und den entsprechenden Unterlegscheiben Schritt 4 Befestigen S...

Страница 28: ...5 5B KOMMUNIKATIONSVERBINDUNG EN GPRS Schritt 1 Pr fen Sie ob die Signalst rke ausreicht 5 6 OPTIONALER DPM SEPARAT ERH LTLICH Schritt 1 Beachten Sie das DPM Installationshandbuch in Verbindung mit di...

Страница 29: ...nd die Verbindung Auf dem Display sollte der Startbildschirm angezeigt werden siehe unten Schritt 3 Datum und Uhrzeit m ssen als grauer Text angezeigt werden Wenn roter Text angezeigt wird ist das SME...

Страница 30: ...lug Charge verwenden wird die Sitzung automatisch gestartet Wenn Sie sich zuerst identifizieren m ssen streichen Sie Ihre Ladekarte ber die LED Die LED blinkt gr n um die Karte zu authentifizieren Nac...

Страница 31: ......

Отзывы: