5.5 COMMUNICATION CONNECTION(S)
For UTP connection (preferred) proceed with 5.5a,
for GPRS connection proceed with 5.5b;
(refer to 3.4 & 3.5 Product Overview)
5.5A COMMUNICATION CONNECTION(S) (UTP)
Step 1; Feed the UTP cable(s) through the rubber
stop(s) on the data cable inlet and then connect it to
the Ethernet port(s), like indicated in the ‘overview of
connections’ section;
Step 2; Connect the UTP to an internet enabled router
with DHCP;
5.5B COMMUNICATION CONNECTION(S)
(GPRS)
Step 1; Check and make sure signal strength
is sufficient;
5.6 OPTIONAL DPM (PURCHASED
SEPERATLY )
Step 1; Make sure to follow the DPM installation manual
in conjunction with this manual.
Step 2; Check if the Phase 1 in chargepoint match the
Phase 1 of the DPM device. If not, correct that first.
Step 3; Feed the UTP cable through the rubber stops on
the data cable inlet and then connect the RJ12 (6P6C)
connector
to the P1 port. Connectors on this cable should be
straight, which means the same order on both sides of
the cable.
Step 4; Contact New Motion after step 5.7 for activation.
5.7 FINISHING UP (CLOSE ENCLOSURE)
Step 1; Check and make sure that the rubber enclosure
seal is properly in place on the enclosure edge all
around;
Step 2; Place the enclosure cover on the charge point;
Step 3; Hand-tighten the four M4 x 12mm bolts provided
around the socket so that the cover closes on the rubber
seal but the rubber seal does not deform;
Step 4; Hand-tighten the other two M4 x 12 mm bolts
provided in the bottom of the cover;
Step 5; Turn the socket lid or dummy socket clockwise
in the cover and hand-tighten the M4 x 20mm bolt
provided;
Step 6; Switch on power to the charge point;
Step 7; Wait until charge point is fully started up (+/-10
minutes, LED should be off);
Step 8; Check that the charge point is connected to the
network. A quick check can be done via chargeportal.
newmotion.com/test. Simply enter the serial number
into the search field and click “Search”. “Online” should
appear after the serial number. If “Online” does not
appear, check whether the charge point is properly
connected and try again. For persistent issues, please
contact NewMotion.
Step 9; If configuration of the charge point power
settings is needed (for example lower Amp settings)
please contact NewMotion;
5.8 CHECK FUNCTIONING
Step 1; Power on the chargepoint and let it start up (give
it a few minutes);
Step 2; Check start screen and connection, the display
should show the initial start screen as shown below;
Step 3; The date and time need to show up as grey
text. If it shows red text the SMED is not synchronised
(backoffice connection issue) or not yet fully started up;
Step 4; You can refer to the user manual for more use
related instructions*;
*Alternatively the owner/operator manual can also be
consulted.
5. INSTALLATION PROCEDURE