NV-202 VDSL2 Bridge with DIP Switch USER’S MANUAL Ver. A4
7
Chapter 2.
Installing the Bridge
2.1 Hardware Installation
This chapter describes how to install the bridge and establish the network connections. The NV-202 may be installed
on any level surface (e.g. a table or shelf or rail). However, please take note of the following minimum site requirements
before one begin.
2.2 Pre-installation Requirements
Before you start the actual hardware installation, make sure you can provide the right operating environment, including
power requirements, sufficient physical space, and proximity to other network devices that are to be connected.
Verify the following installation requirements:
•
Power requirements:
DC
12V power.
•
The bridge should be located in a cool dry place, with at least
10cm/4in
of space at the front and back for
ventilation.
•
Place the bridge away from direct sunlight, heat sources, or areas with a high amount of electromagnetic
interference.
•
Check if the network cables and connectors needed for installation are available.
•
Do not install phone lines strapped together with AC power lines, or telephone office line with voice signal.
•
Avoid installing this device with radio amplifying station nearby or transformer station nearby.