12
NETAFLEX™ 3G
INSTALLATION MANUAL
ON-SITE PREPARATIONS
D
d
X
1
X
2
X
3
H
Description
Required proportions
D Filling line - pipe diameter
d
Fertilizer/acid lines - pipe diameter:
•
32 mm (1¼") for dosing channels of up to 400 l/hr (106 GPH)
•
40 mm (1½") for dosing channels of over 400 l/hr (106 GPH)
X
1
Length of the pipe upstream from the water meter to the adjacent corner
•
Pipe must be straight
10 x D
X
2
Length of the pipe downstream from the water meter to the adjacent corner
•
Pipe must be straight
5 x D
X
3
Length of fertilizers or acid lines
Max. 10 meter (33 feet)
H Elevation of the fertilizer/acid tanks
Min. 30 cm (12")
Infrastructure required proportions
Hydraulic infrastructure preparation
Before performing the infrastructure installation, consult
, page 12.
Required proportions
To enable optimal operation of the NetaFlex™ 3G, piping must be installed while maintaining the following
proportions.
NetaFlex™ 3G
Filling line flow rate and pressure requirements
In order to enable the NetaFlex™ 3G operation, the following requirements must be met.
•
Source water should enter the NetaFlex™ 3G at a flow rate equal to the maximum flow rate required
for the field.
If the flow rate at the inlet of the NetaFlex™ 3G is insufficient, the low level switch will be activated
and the NetaFlex™ 3G operation will be stopped.
Содержание NETAFLEX 3G
Страница 1: ...V 003 02 DECEMBER 2020 NETAFLEX 3G INSTALLATION MANUAL...
Страница 29: ......
Страница 30: ......
Страница 31: ......
Страница 32: ...GROW MORE WITH LESS WWW NETAFIM COM...