5.6 Final Check
1- Load the shelves completely
2- Do several selections, check product delivery
It is possible to send your products to the factory, tests will done for correct adjustment.
USUAL PRODUCTS ARE NORMALLY TESTED IN THE FACTORY, ASK FOR THE SETTING
NUMBER OF THE PRODUCT THAT YOU WISH TO SELL AND REFER TO THIS NUMBER WHEN
ORDERING. WE WILL PRODUCE THE VENDOR ACCORDING TO YOUR SPECIFICATIONS.
5.7 Control Setting
All the machine’s contro ald operation settings can be set through the programming routine of the SF01
electronic board.
The programming routine of the electronic board is described in the SF01 PROGRAMMING MANUAL
supplied with the vending machine
i
REFER TO SF01 PROGRAMMING MANUAL
5.8 Start-up
To start-up the Vending machine, work as follows:
•
Assure that the plug is connected to the supply mains.
•
Give power to the Vendor: ppress the luminous green button
MAIN SWITCH situated on the
transformer box inside of the machine
(on the sliding panel next to the cell).
•
The led tubes switch on through the MAIN SWITCH placed on the front part of the transformer box.
•
Execute the programming routine: refer to
SF01
Programming Manual
•
Load the vendor with the desired products
•
Close the vendor door and wait for the general machine check
•
The vendor is now ready for vending.
CAUTIONS: IN CASE OF FAILURE AND/OR BAD PERFORMANCE OF THE MACHINE, CONTACT
ONLY THE QUALIFIED PERSONNEL AT OUR SERVICE CENTER