© NEC Corporation 2019 38
5.2
Installation Setup – Wall Mounting
For the limited space for installation, you may either cut a same size space as the LED display
on the wall, then install the LED display in this space or fix the support structure directly onto
the wall. It requires solid walls. Observe the ventilation requirements, see 3.6 Ventilation
Requirements.
All additional fixation components and tools must be determined by a detailed static calculation
to ensure a safe and high-performance LED system. Front maintenance will be very
convenient.
See section 6.1 for detailed instructions on wall mounting.
Caution!
Risk of personal injury and product damage by unsuitable wall mounting
equipment.
Before starting the installation:
Ensure that the installation site is suitable for the cable routing plan. If
necessary, mark important points of the plan on the wall used for the
installation.
Regarding the installation site: Analyze the wall used for the installation and
the weight of the complete LED Wall (see Table 6). Choose installation
equipment, e.g. tools, screws and dowels, that are suitable for the wall
conditions and the weight of the LED Wall.
Stability hazard:
The device may fall, causing serious personal injury or death. To prevent
injury, this device must be securely attached to the floor/wall in accordance
with the installation instructions.
Table 6: Dimensions and Weight for LED Wall 4×4, 5×5, 6×6
4 × 4 LED Wall
5 × 5 LED Wall
6 × 6 LED Wall
Dimensions incl.
frame (W × H)
2472×1488 mm
3080×1830 mm
3688×2172 mm
Weight
259 kg
381 kg
503 kg