Procedures

Removing Top-Plate and Sub-Plate

• 

Turn 7870-2000 off, remove power cord and Top-plate

• 

Lift the scanner cover, then with flat-blade screwdriver
remove attaching screw, which is located on the front-
right face of the Sub-plate assembly.

• 

Insert screwdriver into slot next to the retaining tab at the
front-left edge of Sub-plate and release the tab.

• 

Push-up the front-end of the Sub-plate to a vertical
position then pull the back-end out from under the edge of
the Tower Cabinet and lift up and off.

• 

Remove thumb screw and Scale board shield which is
located just in front and left of the scanning area

Installing Top-Plate and Sub-Plate

• 

While holding the Sub-plate in a vertical position place the
rear edge under the edge of the Tower Cabinet then bring
the front-edge down until it contacts the mounting
brackets in a horizontal position and retaining tab snaps
into place in the slot within the mounting bracket’s front-
left edge.

• 

Place scanner’s cover back on Sub-plate assembly and
reinsert the attaching screw into the Sub-plate.

• 

Place Top-plate back on scale and apply power to verify
the display indicates “Ready 0.00 lb.”

• 

Reinsert the Scale Board Shield by aligning the shield’s
tabs  and attaching the thumb screw again.

Calibrate Scanner

• 

Do Procedure (Removing Top-Plate and Sub-Plate)  

• 

Temporarily set the Top-plate back on the rubber
bumpers of the scale hinge assembly so the bumpers
reenter the locating sockets

• 

Apply power to the unit again and perform the following
weight placements on the scale, however,  make sure no
vibrations or movements are near scale during this
process.

• 

Depress and hold Scale Zero switch on panel and note
the CAL and PAR readings then release switch.

• 

Lift up the top-plate briefly and replace after depressing
the SW1 calibration switch, located underneath the just
removed scale board shield.

• 

Verify display reads “Ready 0.00 lb.”

• 

Press Scale Zero switch, display says Ready 5.00 lb.

• 

Place 5.00 lb. weight on top-plate

• 

Press Scale Zero switch, display says Ready 15.00 lb.

• 

Add 10.00 lb. weight on top-plate

• 

Press Scale Zero switch, display says Ready 30.00 lb.

• 

Add 15.00 lb. weight on top-plate

• 

Press Scale Zero switch, display says Ready 0.00 lb.

• 

Remove all weights and press Scale Zero switch, display
says Scale Ready 0.00 lb.

• 

Depress and hold Scale Zero switch on panel and record
the CAL and PAR readings then release switch.

• 

Turn off power to unit and remove the top-plate.

• 

Do Procedure (Installing Top-Plate and Sub-Plate)  

• 

To verify place three weights separately in the center of
the Top-plate, verify weights are within a .02 offset.

• 

Place the same weight on 4 different areas on the Top-
plate, verify the weight is within a .02 offset.

Procedures (Continued)

Front Bezel Removal

• 

Turn 7870-2000 off and remove power cord.

• 

Locate tower cabinet at rear of scale

• 

Locate two releases on each side of clear bezel glass

• 

Pull bezels top edge out and down by pivoting on base

• 

Disconnect cables to the status LED’s

• 

Lift Bezel up and out of the tower cabinet.

Front Bezel Installation

• 

Reinsert new or existing Bezel’s bottom in first.

• 

Reconnect the status LED’s

• 

Push back Bezel in place, verify it snapped in position

• 

Reinsert power cord and restart the 7870 device

Scale Board Replacement

• 

Do Procedure (Removing Top-Plate and Sub-Plate)  

• 

Disconnect the load cell (J1) and scale (J2) cable.

• 

Remove the board screw and carefully pry three boards
retainers to release the Scale Board.

• 

Insert the new board and reapply the board screw.

• 

Do Procedure (Calibrate Scanner) starting on 2nd step

Digital Board Replacement

• 

Do Procedure (Front Bezel Removal)

• 

Jumpers stated are (Digital Board / LC-Digital Board).

• 

Remove 4 screws from the sides of tower and lift straight
up,  disconnect display cable (J5 / J4) if used.

• 

Remove Indicator cable (J2), Speaker (J4 / J1), Scale
Cable (J3), Video Board (J1 / J5)

• 

Pull out the digital board in its connector and swap the
firmware in these areas (U19, U22, U26 /  U15, U18).

• 

Reinsert  a new Digital or LC-Digital Board.

• 

Install the Video Brd. cable (J1 / J5), Scale Cable (J3),
Speaker (J4 / J1), and Indicator cable (J2).

• 

Reconnect any display cables to the tower before placing
tower case back on,  tighten the 4 tower screws to hold it
in place.

• 

Do Procedure (Front Bezel Installation) & (Calibrate)

Fan Replacement

• 

Do Procedure (Removing Top-Plate and Sub-Plate)  

• 

Do Procedure (Front Bezel Removal)

• 

Remove 4 screws from the sides of tower and lift straight
up,  disconnect display cable (J5 / J4) if used

• 

Remove ground wire to optics assembly,  lift forward, up
and out of unit and place upside-down on table.

• 

Unplug cable (J6) from video board.

• 

Squeeze output end of duct and detach then release duct
clips on video board and lift duct over (J6).

• 

Slide fan out and new fan back in the same position and
make sure cable (J6) is not between duct and fan.

• 

Reapply the duct clips and connect the end of the duct to
video board by squeezing it in place.

• 

Reconnect (J6) to video board and place optics assembly
back in unit and tighten ground wire.

• 

Reconnect any display cables to tower cabinet before
placing it back on then tighten the 4 tower screws.

• 

Do Procedure (Front Bezel Installation)

• 