04
HI-LINE LV Fan Convector
7.0 Water Connections
l
Connect unit to system flow and return pipes using the two
15mm isolating valves (see fig. 3).
l
Ensure system is flushed in accordance with recognized best
practice and a suitable inhibitor is added to the system as
necessary.
l
Open valves fully, check pipe connections for leaks and vent
the heat exchanger - see Commissioning Procedure.
//
//
//
//
///
///
///
///////
/////////
//////
//////////
///////////////////////////
/////
/////
Fig. 3
5.0 Preparation
Before proceeding with the installation, unpack the carton
contents and check against the checklist below:
1.
HI-LINE LV unit.
2.
15mm isolating valves (1 pair).
3.
Instruction manual.
4.
Warranty card.
5.
Fixing kit (rubber mounts, cable gland and equipotential bond
pipe clamp).
6.
Transformer.
6.0 Fixing
l
Using the fixing dimensions below (see fig. 2), mark the fixing
hole positions on the wall.
l
Drill and plug the wall for No. 8 x 40mm round head wood
screws ensuring that the wall plugs are suitable for the wall
type.
l
Remove the backing from the self-adhesive washers and place
on screws with adhesive side towards the point.
l
Tighten the screws into the wall leaving about 9mm
projecting.
l
Press adhesive washers to the wall.
Remove the outer casing as follows:
l
Remove the 2 screws from the underside of the unit (see fig. 2).
l
Lift off the outer case.
l
Fit chassis on to mounting screws and tighten.
Note:
Before proceeding with pipe-work connections check that
the unit is level. If the right hand end is lower than the left then
the ability to vent the unit may be restricted.
When water connections and electrical connections have been
completed and the unit has been vented, fit the outer cover and
secure with fixing screws.
///
///
///
//
//
//
//
//
Fig. 2
xxxxxx HiLine LV manual_Layout 1 27/06/2011 09:39 Page 5