Installation
trench depth and large enough for a
person to work. Lay water-supply
line and waste line (if required) into
Prepare trench for water-supply line
and waste line (if required). Below
fountain location, prepare hole to
trench, allowing extra line length to
be trimmed during hook-up.
Install drinking fountain fully as-
sembled as shipped. Position
drinking fountain at desired location.
Brace fountain by laying two boards
across hole and under fountain
base, one on either side of black
pipe. To ensure plumb installation,
lay a bubble level on fountain bowl
and adjust bracing boards until unit
is level.
Purge water-supply line. Connect
water-supply line, trimming line
length as necessary. Depending on
code and design requirements,
drain may be open, French or
sanitary connection. For open
drain, wrap bottom opening with
filter fabric and place a minimum of
three cubic feet of large, broken
rock around opening.
Back-fill trench and hole, leaving
sufficient depth in hole to accom-
modate concrete slab. Compact
back-filled earth. Remove bracing
boards.
Prepare hole surrounding fountain
for concrete slab. Spread and
compact gravel as necessary. Pour
concrete up to bottom of drinking-
fountain pedestal base. Finish
concrete as necessary.
Maintenance instructions
Remove nuts and bolts from
flanges underneath drinking-
fountain bowl. Remove nut and bolt
securing pedal to pedestal. Care-
fully lift bowl straight up, removing
bowl-and-line assembly.
Unscrew packing ring from valve
body at bottom of assembly and
remove seat-washer screw. Re-
move and replace seat washer, cup
washer and ring washer. Replace
seat-washer screw and packing
ring.
Carefully lower bowl-and-line
assembly into pedestal base. As
bowl approaches top of pedestal,
lower gently until valve body
encounters valve stem below grade.
Carefully work bowl-and-line
assembly until valve body slips
around valve stem, allowing bowl to
drop freely to top of pedestal.
Replace nut and bolt through
pedestal base, working pedal to
ensure that bolt passes through
pivot hole in pedal lever. With
pedal facing front, ensure that
mouthguard is oriented at right and
that mating flanges underneath
bowl are aligned. Replace nuts and
bolts through mating flanges
underneath bowl. Note that upper
flanges incorporate recesses to
secure square nuts.
Please visit
for most current specifications.
www.murdock-supersecur.com
Please visit
for most current specifications.
www.murdock-supersecur.com
MURDOCK-SUPER SECUR
15125 Proctor Avenue
City of Industry, CA
91746 USA
Phone 800-453-7465
626-333-2543
Fax 626-855-4860
A Member of
Acorn Engineering's
Family of Companies