9 Commissioning of on-load tap-changer by transformer manufacturer
Maschinenfabrik Reinhausen GmbH 2015
209
4349315/00 EN
VACUTAP® VR®
Commissioning of on-load tap-changer by
transformer manufacturer
Bleeding on-load tap-changer head and suction pipe
Before first commissioning, the on-load tap-changer head and the suction
pipe on pipe connection S must be bled.
Bleeding on-load tap-changer head
1.
Open all forward and return valves in the pipe system.
2.
Remove screw cap on air-vent valve E1 on the on-load tap-changer
head cover.
Figure 283: Screw cap
3.
Use screwdriver to lift valve tappet on air-vent valve E1 and bleed on-
load tap-changer head.
Figure 284: Valve tappet
4.
Seal air-vent valve E1 with screw cap (tightening torque 10 Nm).
9
9.1
9.1.1
Содержание VACUTAP VR
Страница 1: ...On Load Tap Changer VACUTAP VR Installation and Commissioning Instructions 4349315 00 EN ...
Страница 246: ...14 Appendix Maschinenfabrik Reinhausen GmbH 2015 246 4349315 00 EN VACUTAP VR ...
Страница 248: ...14 Appendix Maschinenfabrik Reinhausen GmbH 2015 248 4349315 00 EN VACUTAP VR ...
Страница 266: ......
Страница 267: ......