Check for successful completion of the refrigerant oil recovery operation.

 Turn the dipswitches 1-4, 1-5, 1-6, and 1-7 to ON to verify that the refrigerant oil recovery operation is completed. “S-1” or “r-1” on

the outdoor unit’s LED indicates a successful completion.

“S-1”  “r-1”: The refrigerant oil recovery operation is successfully completed. Go to the next procedure.
“S-1”  “r-0”: The refrigerant charge adjustment is not completed, but regular air conditioning operation can be started. If there was excess

refrigerant that had not been charged, charge it through the low-pressure check joint (CJ2) during the air conditioning operation.

“S-0”  “r-1”: The refrigerant oil recovery operation is not completed. To restart the refrigerant oil recovery operation, set the dipswitches 3-1 and

4-8 to ON in that order.

“S-0”  “r-0”: The refrigerant oil recovery operation is not completed. To restart the refrigerant oil recovery operation, set the dipswitches 3-1 and

4-8 to ON in that order.

8

Disconnecting the cylinder

 After completing the oil recovery operation, close the valve on the cylinder, and disconnect the cylinder within five minutes.

9

Recording the amount of refrigerant that was charged

 Write on the control box panel the amount of refrigerant charged. 

0

Closing the valve on the connecting port to the refrigerant circuit

 Close BV3 completely. The refrigerant oil recovered from the existing pipes is sealed in an oil recovery vessel.

Procedure 8

LED

Procedure 9

Procedure 10

Procedure 11

S

O

O

S

Compressor side

Oil-recovery side

<Factory setting> <After the oil-recovery test run>

A

A

B

C

Turn the valve clockwise by 90 degrees.
* Use a tool if necessary.

Lever

(Cap tightening torque: 20-25N•m

 (200-250 kg•cm))

Rotation direction

WT06218X01_en.fm  Page 7  Tuesday, December 14, 2010  4:19 PM

Содержание REPLACE MULTI PURY-RP200YJM-B

Страница 1: ...LLECTE D HUILE MINÉRALE RÉCUPÉRATION DE L HUILE FRIGORIFIQUE MANUAL DE INSTRUCCIONES PARA LA RECOGIDA DE ACEITE MINERAL RECUPERACIÓN DE ACEITE REFRIGERANTE RACCOLTA DELL OLIO MINERALE RECUPERO DELL OLIO REFRIGERANTE MANUALE DI ISTRUZIONI MANUAL DE INSTRUÇÕES DE RECOLHA DE ÓLEO MINERAL RECUPERAÇÃO DO ÓLEO REFRIGERANTE Air Conditioners For Building Application Outdoor Unit PURY RP200 250 300YJM B BS...

Страница 2: ...ort to the refrigerant circuit Evacuation port high pressure side A port through which refrigerant for the indoor units is charged D Service port on the low pressure valve Connecting port to the refrigerant circuit Evacuation port low pressure side A port through which refrigerant for the indoor units is charged E A valve to be closed after the completion of refrigerant oil recovery operation BV3 ...

Страница 3: ...hen the pressure sensor reads 18 8 kg cm2 G Item No 58 The unit of pressure is in kg cm2G Use the following conversion formula to convert the displayed value into a value in SI unit MPa SI unit MPa Displayed value kg cm2 G 0 098 Flag display Each set of two lines in vertical alignment indicates a flag Example Outdoor unit in the 3 minute restart delay mode Item No 14 2 Table of items that can be m...

Страница 4: ... BC controllers To calculate the required amount of refrigerant charged for the pipes refer to 10 1 Calculation of additional refrigerant charge in the installation manual on the CD ROM If there is excess refrigerant that cannot be charged use it during oil recovery operation at step 4 cooling operation After charging the required amount of refrigerant to the existing pipes open the valve so that ...

Страница 5: ...is insufficient the units may stop during refrigerant oil recovery or it may take longer than usual to complete a test run 5Setting the unit address and checking for proper system operation Set the unit address turn on the power and check for proper operation of the system If an attempt is made to operate the outdoor unit before the refrigerant oil recovery operation is complete an error code 7116...

Страница 6: ...igerant charge Do not exceed the maximum amount If the refrigerant oil recovery operation does not finish after the maximum amount of refrigerant is charged close the valve on refrigerant cylinder and wait for the operation to be completed automatically If the cylinder runs out of refrigerant during the refrigerant oil recovery operation continue the operation and replace the cylinder I If more th...

Страница 7: ...pswitches 3 1 and 4 8 to ON in that order S 0 r 0 The refrigerant oil recovery operation is not completed To restart the refrigerant oil recovery operation set the dipswitches 3 1 and 4 8 to ON in that order 8Disconnecting the cylinder After completing the oil recovery operation close the valve on the cylinder and disconnect the cylinder within five minutes 9Recording the amount of refrigerant tha...

Страница 8: ...Electromagnetic Compatibility Directive 2004 108 EC Pressure Equipment Directive 97 23 EC Please be sure to put the contact address telephone number on this manual before handing it to the customer HEAD OFFICE TOKYO BLDG 2 7 3 MARUNOUCHI CHIYODA KU TOKYO 100 8310 JAPAN Authorized representative in EU MITSUBISHI ELECTRIC EUROPE B V HARMAN HOUSE 1 GEORGE STAREET UXBRIDGE MIDDLESEX UB8 1QQ U K WT0621...

Страница 9: ...s Replace Belfast PURY RP200 300YJM B Declaration of Conformity PURY RP200 300YJM B Installation Manual WT06216X01 PURY RP200 300YJM B Mineral Oil Collection Instruction Book WT06218X01 PURY RP200 300YJM B Parts Catalogue BWE1024B PURY RP200 300YJM B Service Manual HWE10140 Replace Multi VRF Data Book MEE15K060 PURY RP200 300YJM B Parts Catalogue BWE10240 ...

Страница 10: ......

Отзывы: