Dryer Assembly and Setting
PELLERIN MILNOR CORPORATION
2.
Site Requirements
2.1.
Dryer Environment
—The dryer must not be installed or stored in an area where it will be
exposed to water and/or weather.
2.2.
Clearances
—Observe the following:
• Sufficient clearances must exist to move the machine into the laundry. All openings and
corridors through which equipment must pass must be of sufficient size to accommodate the
sizes of the skidded assemblies (see the dimensional drawing). It is occasionally possible to
reduce the overall dimensions by removing piping and by other special modifications.
Consult the Milnor factory for more information.
• Provide sufficient clearance around machine for normal operation and maintenance
procedures.
• Ensure sufficient clearance between hot surfaces, such as the dryer exhaust vent, and any
combustable building materials.
• Ensure sufficient ventilation exists for the heat and vapors of normal operation to dissipate.
• Provide adequate airflow for optimum machine performance. Normally, this means
connecting the machine to an outside air source.
2.3.
Foundation
—The machine must be anchored in accordance with the installation instructions.
The floor and/or all other support components must have sufficient strength (and rigidity with
due consideration for the natural or resonant frequency thereof) to withstand the fully loaded
weight of the machine including the wet goods and any repeated sinusoidal (rotating) forces
generated during its operation. Determining the suitability of floors, foundations, and other
supporting structures normally requires analysis by a qualified structural engineer.
3.
Assembly
3.1.
Installing the Legs on the House
—It is usually easiest to install the legs on the house
then use a fork lift to set the machine in place.
1. Read all related tags prior to assembly.
2. Verify that the doors are closed and secured.
3. Unfasten house from the shipping skid. Once skids are removed, take care in placing forks
under the machine.
Do not allow forks to come in contact with valves, piping, motors,
etc., located under the machine.
4. Install the provided foam seal along the path indicated by decals on the machine. This seal is
only installed on the left side machine of a left and right pair (
5. Raise the house using the three designated lifting plates located on the top of the machine.
6. Install the legs and filler plates on the house.
7. Remove the spreader bar (
8. Carefully move the machine into place.
9. Repeat the assembly process as required for the adjacent machine (if paired).
33
Содержание 6458
Страница 2: ......
Страница 8: ......
Страница 9: ...Safety 1 5 ...
Страница 32: ......
Страница 33: ...Installation 2 29 ...
Страница 75: ...Installation Drawings 3 71 ...
Страница 76: ......
Страница 77: ...73 ...
Страница 78: ...74 ...
Страница 79: ...75 ...
Страница 80: ......
Страница 81: ...77 ...
Страница 82: ...78 ...
Страница 83: ...79 ...
Страница 84: ...80 ...
Страница 85: ...81 ...
Страница 86: ......
Страница 87: ...83 ...
Страница 88: ...84 ...
Страница 89: ...85 ...
Страница 90: ...86 ...
Страница 91: ...87 ...
Страница 92: ...88 ...
Страница 93: ...89 ...