The following procedure explains how to re-install the chain should this ever become necessary. As needed,
refer to the Beaters and Drive Assembly parts detail in Appendix A at the back of this manual.
1.
Disconnect the spreader from the tractor.
2.
Securely block up the right side of the spreader, and remove the right side wheel.
3.
Remove the right safety shield by removing the three (3) nuts holding the shield in place.
4.
At the front of the spreader, pull up on the right lever to engage the beater drive components.
5.
As shown in Figure 3D, re-install the chain around the small rear sprocket.
6.
Re-install the chain over the top idler sprocket.
7.
Re-install the chain around the bottom idler sprocket.
8.
Push the operating lever down (right side) to disengage the beater drive.
9.
Verify that the chain is positioned properly over and around all sprockets as shown in Figure 3D.
10.
Re-install the safety shield with the three (3) nuts to hold it in place.
11.
Re-install the wheel and torque the wheel bolts to 60 ft. lbs. Remove the safety blocking.
Figure 3D - Beater Drive Chain Installed in the Proper Position