INSTALLATION
As a first step, proceed with the following drawings:
A vertical l
ine up to the ceiling or up to the upper limit, at the center of the area in which the hood
is
to be fitted.
A horizontal line
A
at
970 – 1070
mm above the cooker top.
A horizontal line
B
at a
X
mm above the horizontal line
A
.
A horizontal line
C
at a 2
43
mm below the horizontal line
A
.
Mark Points:
Mark a point
(1)
on the horizontal line
A
,
80
mm to the vertical reference line.
Repeat this operation on the other side and on the vertical reference line, checking that the
three marks are leveled.
Mark a point
(2)
on the horizontal line
B
,
60
mm to the vertical reference line.
Repeat this operation on the other side, checking that the two marks are on the same
horizontal line.
Mark a point
(3)
on the horizontal line
C
,
100
mm to the vertical reference line
.
Repeat
this operation on the other side , checking that the two marks are leveled.
Fix the brackets :
Drill holes at the marked points with a ɸ10 mm drill bit.
Insert the Wall Plugs 11 into the holes.
Fix the hood fixing bracket
20
with 3 screws
10
(5 x 50) at the horizontal line A.
Fix a Chimney fixing bracket
21
with 2 screws
10
(5 x 50) at the horizontal line
B
.
WALL DRILLING AND BRACKET FIXING
100
100
C
(3)
Option Chimney
X
1
400X390 160-500
2
500X490 260-700
Vertical reference line
243
2
3
4
6
7
8
9
10
11
5