Connecting Gases
Gemini VII 2390 Confirm
42 Gemini VII 2390 Confirm Installation Instructions and Checklist
Feb 09
6. Purge the air from the gas line.
a. Open the regulator shut-off valve.
b. Open the gas bottle shut-off valve and flow gas for 10 to 30 seconds.
c. Close the gas bottle shut-off valve.
Connecting the Gas to the Instrument
The instructions below show how to attach the analysis gas to the instrument. Repeat the steps,
using the He port, to attach Helium to the instrument.
1. Loosen, then remove the plug from the port.
2. Insert the gas line into the port and hand-tighten the connector nut.
Regulator
Control knob
Regulator
Shut-Off
valve
Gas Bottle
Shut-Off valve
Be sure the gas bottle is closed before connecting the gas line to
the instrument.