MPPT INSTALLATION
7
3. MPPT INSTALLATION
3.1
MPPT minimum installation clearance distance
Maintain a minimum clearance of 20cm below and above, 10cm on the sides of the MPPT to ensure
unhindered air circulation. Mount the solar charge controller as close as possible to the batteries.
3.2
MPPT Installation Instructions:
Read the installation instructions before installing the MPPT.
The MPPT is designed for indoor applications only.
The mounting position should allow for sufficient ventilation and the minimum clearance
distance between MPPT’s and other objects, trunking as above.
Mount the MPPT at eye level in order to allow the user to read the LED indicators.
The MPPT must be mounted in a vertical position against a solid wall.
Do not install the MPPT in a sealed container.
Do not install the MPPT near water or in damp environments.
Do not install the MPPT where it would be exposed to direct sunlight or near heat.
Do not install the MPPT on a wooden surface. Only install the MPPT on flat concrete,
stone or metal surfaces.
Do not block off the aluminium heat sink and don’t leave objects on top of the MPPT.
Do not expose the MPPT to corrosive battery gases. Corrosion is not covered by
warranty.
MPPT operatin
g environment temperature should not exceed: 0˚C - 40˚C.
Ensure that connecting cables are of adequate size.
100 mm
100 mm
100 mm
200 mm
200 mm
200 mm
200 mm