4. WATER CIRCUIT
Pipe installation must be carried out in accordance with current norms and directives .
The split box is not equipped with shut off valves on the water side (XL1 and XL2),
these must be installed to facilitate any future servicing .
When operating the split box free flow in the climate system is recommended for
correct heat transfer . This can be achieved by use of a bypass valve . If free flow
cannot be ensured, it is recommended that a buffer tank is installed .
Install the supplied ball valve with particle filter on the climate system return pipe,
XL2, to protect the heat exchanger in the split box .