6.6 Primary leakage current
Refer to master instrument Instruction manual, chapter
Single test
measurements
, subchapter
Primary leakage
for detailed information.
Procedure:
Item
Comment
Prepare test system.
See
chapter 4.3 Working
Connect power supply plug of tested welding
machine into proper test socket.
Enable L-N change parameter on the master
instrument (for single-phase welding machines)
Optional
Start measurement.
Wait until measurement is finished or stop the
measurement.
Check result(s).
Store result(s).
Optional
Figure 6.6:
Primary leakage current measurement
Warning:
During the test, DUT is powered as for normal operation. Pay attention on
possible electric shock!
Note:
Consider any displayed warning before starting measurement!