E-BAM-9805 Manual Rev B.docx
Page 14
2.6 Power-up Settings Verification and Automatic Self-Test
The E-BAM will present several setup parameters for verification whenever it is powered on. These
setup screens can also be viewed or edited in the SETUP menu under the main E-BAM menu
system. See section 3.6 for detailed descriptions of the SETUP parameters.
When power is applied to the E-BAM, the unit will show the startup splash screen for the
touchscreen display for a moment, then display the welcome screen as shown in Figure 2-6.
Figure 2-6 Welcome Screen
Press the SETUP button and the clock screen is displayed (see Figure 2-7). If the time and date are
correct, press the YES button again. If the date or time need to be changed, press the EDIT button.
See section 3.6.1 for details on changing the date and time.
Figure 2-7 Verifying the Clock
After the time is verified, the unit will display the Settings screen shown in Figure 2-8 below. If the
settings need to be changed, press the green bordered value box to be updated and the associated
edit screen will be displayed.
Figure 2-8 Verifying the Initial Settings
Press OK if the settings are correct, after confirming or setting the Location and Data Average
settings, the E-BAM will need to check whether a roll of filter tape installed. The monitor will then
check the tape installation. If no tape is detected, the unit will prompt for installation of a new roll: