P 5
Please retain product label and instructions for future reference
25
88
8
20
8
Step 8
Rest the first roof panel on top of the
supports and secure with 20x40mm
screws as shown in the illustration.
*Ensure to align the screws with each
roof support bar.
Fix the roof (internally) to the roof
support bar using 8x40mm screws
(making sure the roof framing sits
behind the support bar)
.
Repeat this process with the second
roof panel, ensuring there is an equal
amount of overhang either side of the
building.
56x40mm Screws
40mm
screw
Pre drill
hole
7
20
Step 9
Place the front roof onto the assembly
securing into place using 4x40mm
screws as shown in the illustration.
Following the same method outlined in
step 8 fix the front roof (internally) to the
roof support bar using 4x40mm screws.
8x40mm Screws
40mm
screw
Pre drill
hole
40mm
screw
Pre drill
hole
80mm
screw
Step 6
Place the first ridge bar
inside the building and
line up with the upright
framing on each gable.
Align the back edge of the
ridge bar with the top of the
gable. Once in place mark
the position on both sides
with a pencil.
Place the roof support block
to the pencil mark and
secure in place using
2x40mm screws per block.
*Repeat this process on both sides
with the remaining roof support
bars.
Place the ridge bar(s) on top
of the attached blocks and
secure through the outside
of both gables using
2x80mm screws per side.
14x40mm Screws
14x80mm Screws
a
b
a
15
28
15
b
*Hint: When fitting the roof bar pencil mark the centre
of the roof support bar and follow down onto the gable
at a right angle, this will give you a guide to fix the
support bars in place.