Please retain product label and instructions for future reference

             

25

88

8

20

8

Step 8

Rest the first roof panel on top of the

supports and secure with 20x40mm

screws as shown in the illustration.

*Ensure to align the screws with each

roof support bar.

Fix the roof (internally) to the roof

support bar using 8x40mm screws 

(making sure the roof framing sits 
behind the support bar

.

Repeat this process with the second

roof panel, ensuring there is an equal

amount of overhang either side of the

building.

 

56x40mm Screws

40mm 

screw

Pre drill 

hole

7

20

Step 9

Place the front roof onto the assembly

securing into place using 4x40mm 

screws as shown in the illustration.

Following the same method outlined in

step 8 fix the front roof (internally) to the

roof support bar using 4x40mm screws.

 

8x40mm Screws

40mm 

screw

Pre drill 

hole

40mm 

screw

Pre drill 

hole

80mm 

screw

Step 6

 

Place the first ridge bar  

 

inside the building and  

 

line up with the upright  

 

framing on each gable.  

 
 

Align the back edge of the  

 

ridge bar with the top of the

 

gable. Once in place mark  

 

the position on both sides  

 

with a pencil. 

 

Place the roof support block 

 

to the pencil mark and  

 

secure in place using   

 

2x40mm screws per block.

*Repeat this process on both sides 
with the remaining roof support 
bars.

 

Place the ridge bar(s) on top  

 

of the attached blocks and 

 

secure through the outside

 

of both gables using   

 

2x80mm screws per side.

14x40mm Screws
14x80mm Screws

a

b

a

15

28

15

b

*Hint: When fitting the roof bar pencil mark the centre

of the roof support bar and follow down onto the gable 

at a right angle, this will give you a guide to fix the 

support bars in place.

Содержание 03HEL1010DDFW-V2

Страница 1: ...is placed on a suitable base BUILDING A BASE When thinking about where the building and base is going to be constructed Ensure that there will be access to all sides for maintenance work and annual treatment Whilst all products manufactured are made to the highest standards of Safety and in the case of childrens products independently tested to EN71 level we cannot accept responsibility for your s...

Страница 2: ... End 2536mm 24 Door Bar 1705mm 25 2x Posts 2044mm 26 2x Door Beading 1711mm 27 Finial 31 Turn Button QTY 2 30 Flush Hinge QTY 6 Key Plate 29 28 Door Handle QTY 2 32 Mortice Lock 33 Barrel Bolt QTY 2 34 x4 Rain Guard 580mm Plain Side QTY 2 Felt 50mm Screw x57 40mm Screw x105 Felt Tacks x185 30mm Screw x133 60mm Screw x80 30mm Black Screw x2 Nail Bag Pre Assembly Remove the transportation blocks fro...

Страница 3: ...the screws provided Fix the door handles and the metal bar spindle using 8x30mm screws Ensure the mortice lock opens and closes freely If not remove the lock and turn the catch around using the small grub screw 8x30mm Screws 30mm screw Pre drill hole Step 2 Continued Fix the door bar to the inside of the slave door with 6x30mm screws as shown in the illustration Attach the door beading strips to t...

Страница 4: ... a b b b b b b Step 4 Fix the second gable to the plain side at the corner using 3x60mm screws Do NOT secure to the floor until the roof has been fitted Attach the posts to the front of each gable with 3x60mm screws per post 9x60mm Screws a b 25 25 2 3 a a a a b b a a Step 5 Secure the left right window panels to the posts using 3x60mm screws per panel Do NOT secure the assembly to the floor until...

Страница 5: ... fix the front roof internally to the roof support bar using 4x40mm screws 8x40mm Screws 40mm screw Pre drill hole 40mm screw Pre drill hole 80mm screw Step 6 Place the first ridge bar inside the building and line up with the upright framing on each gable Align the back edge of the ridge bar with the top of the gable Once in place mark the position on both sides with a pencil Place the roof suppor...

Страница 6: ...hole Please retain product label and instructions for future reference a a a a a a a Step 11 Now the roof has been fitted secure the building to the floor with 36x60mm screws Ensure to align the screws with the floor bearers 36x60mm Screws a Step 12 Cut the felt into 4x strips Roll the felt across the roof in the order shown in the illustration leaving approximatley 50mm of overhang at the front r...

Страница 7: ...he finial over the fascia joint and fix into place with 2x40mm screws 10x40mm Screws 40mm screw Pre drill hole Slave Door Locking Door 18 18 21 17 21 17 17 Please retain product label and instructions for future reference Step 15 Fix the cover trims around the building across the joints on each panel and at the corners using 3x30mm screws per trim 21x30mm Screws Step 16 Attach the turn buttons to ...

Страница 8: ...uards centrally above each window using 3x50mm screws per guard 18x50mm Screws Please retain product label and instructions for future reference 27 37 Step 18 Secure the larger rain guard above the doors fixing into place using 4x50mm screws ensure to screw into the framing above door 4x50mm Screws S IL IC O N E S E A L A N T Hint Silicone seal the back of each rain guard to help reduce water runn...