Creating a mount for the installation kit in a frame construction
►
Commission an architect or design
professional to include the mount for
the installation kit at a suitable point
in the construction drawing.
►
Incorporate two wooden battens into
the frame construction at the planned
installation position:
—
The lower batten (item 1 in
Fig. 44) acts as a support.
NOTICE
► Use a spirit level (item 2 in Fig. 44)
to check that the lower batten is
exactly horizontal as this is the only
way to ensure that any condensa-
tion will be carried outside by the
2° pipe fall in the installation kit
(item 3 in Fig. 44).
—
The upper batten (item 4 in Fig. 44) is used to fix the installation kit.
NOTICE
—
The installation kit is fixed in the optimum position with a vertical distance of 661 mm
between the lower and upper batten (see Fig. 44). You can insert the installation kit
temporarily while fixing the battens to ensure that the kit will fit perfectly.
— Maintain the following minimum distances:
— At least 435 mm between the vertical framing members
— At least 300 mm between the top edge of the wall box and the ceiling
— At least 50 mm between the side and bottom edges of the wall box and adjacent
surfaces
Fig. 44: Creating a mount for the installation kit in a
frame construction – dimensions in millimetres
min. 435
661
min. 300
1
2
3
4