FORM #1132   ME990-3F IOM 

Rev C 2/3/21 

 

 

Operation 

 
Since the ME990-3F internal valve is most often used on 
transport trucks, the following procedure applies to that 
type of application. 
 

1.

 

Always open the internal valve before starting 
the pump and before opening the valve on the 
pump outlet. 

2.

 

Normally leave the pumping system "wet" to 
avoid repeated drying of the seals and to reduce 
time in opening the internal valve. Drain the 
piping only when codes or safe operating 
practices require. 

3.

 

If piping is dry or at lower pressure than the 
tank, open the internal valve only about halfway 
for a few seconds so that line pressure can 
equalize before fully opening the operating 
lever. The valve may not equalize if the 
operating lever is moved to the fully open 
position. 

4.

 

Avoid flow surges which could close the built-in 
excess flow valve. If the valve should "slug" shut, 
stop the pump, close the nearest downstream 
valve, and move the lever to mid-position to 
speed equalizing until the valve opens. There will 
be an audible click when the valve opens. 

5.

 

Always leave the valve closed except when 
transferring product. 

6.

 

All valves should be completely open when 
pumping. (Throttling type valves could prevent 
the excess flow valve from closing when 
required.) 

7.

 

The operator must always be aware of where 
the remote closure controls are located and 
know how to operate the controls if any 
emergency requires valve closure. 

 
 

Troubleshooting 

 
Internal Valve Will Not Open
: This could be due to leakage 
downstream, engaging the pump too soon or from 
excessive wear in the internal valve. If excessive volume is 
in the downstream system, a longer time is required to 
equalize the pressures {tank and downstream} before the 
pump can be engaged. To determine if the valve pilot seat 
is opening, install a gauge downstream of the valve, 
operate the valve actuator; if pressure does not build-up 
to the tank pressure, the valve pilot seat is not open. This 
test should be done with the pump off. If the pilot is not 
opening, it may be plugged with dirt or some internal part 
may be broken. If by operating the lever manually it can be 
rotated past the fully open position, there is something 
wrong internally and the valve must be disassembled. 
 
Premature Valve Closure
:  This can be caused from 
engaging the pump too soon, by an underrated excess 
flow valve spring, or by an improperly connected internal 
valve operating lever which does not fully open the valve. 
The trouble could also be from a valve that has its inlet 
port obstructed or from sudden line surges. In order to 
check the valve opening travel, operate the lever manually 
to the full travel, wait until valve opens (usually about 15 
seconds), then engage the pump. If the excess flow closes, 
the points mentioned above should be investigated. 
 
Internal Valve Will Not Close: The stub shaft could be 
binding or the stem could be bent in the valve. Before 
disassembling the valve, check the actuator mechanism to 
see that it operates freely by disconnecting it from the 
valve lever and cycling it several times. Also, operate the 
valve lever manually. If it sticks in the open position, the 
packing and bushings should be replaced. This should free 
the operating mechanism if the valve has not been 
damaged internally. Refer to the "Maintenance" section. 
 

FIGURE 4: Operational Schematic 

Содержание ME990-3F

Страница 1: ...tream of a pump may not actuate the excess flow valve If any break occurs in the system or if the excess flow valve closes the system should be shut down immediately WARNING These products contain a c...

Страница 2: ...ME990 3F FORM 1132 ME990 3F IOM Rev C 2 3 21 FIGURE 2 ME990 3F INSTALLATION SCHEMATIC 1 25mm MINIMUM...

Страница 3: ...r before putting the valve into service Selectively Filling Manifolded Tanks MEC internal valves provide positive shutoff only in one direction from out of the tank to downstream of the valve The inte...

Страница 4: ...esult in serious or fatal personal injury or property damage from a fire or explosion DOT Passive Shutdown Equipment Requirement DOT regulations 49CFR 173 315 n 2 require certain cargo tanks transport...

Страница 5: ...ear in the internal valve If excessive volume is in the downstream system a longer time is required to equalize the pressures tank and downstream before the pump can be engaged To determine if the val...

Страница 6: ...repair can create a hazardous situation which could result in serious or fatal personal injury or property damage A simple preventative maintenance program for the valve and its controls will elimina...

Страница 7: ...e Seal 1 11 Valve Poppet 1 12 Bleed Disc 1 13 Lock Nut 1 14 Closing Spring Washer 1 15 Closing Spring 1 16 Spring Guide 1 17 Stem Bushing 1 18 Valve Cage 1 19 Cage Screw 4 20 Stub 1 21 Gland Bushing 2...

Страница 8: ...ME990 3F FORM 1132 ME990 3F IOM Rev C 2 3 21...

Отзывы: