20001316

Framing

Framing can be constructed before or after the fireplace 
is set in place, however, most installers build the frame 
before setting the fireplace.
Frame fireplace with 2 x 4 lumber or heavier materials.  
Refer to framing dimensions in Figures 1 or 2  for basic 
fireplace specifications. Headers and support studs 
must be turned on end as illustrated in Figure 2, Page 
4.

NOTE:

  Framing should be positioned to accommodate 

wall covering and fireplace facing material.

Chimney Set-up

Since you have already preplanned the chimney run, 
you should know exactly how the installation is to be ac-
complished — how much pipe is required, the number 
of elbows, if any, and type of termination to be used.

CAUTION:  REPORT TO YOUR DEALER ANY PARTS 
DAMAGED IN SHIPMENT, SPECIFICALLY CHECK 
THE END CONNECTION OF CHIMNEY SECTIONS 
AND ELBOWS.

Straight-Up Chimney Installation

To locate the centerline of the flue put the fireplace in 
final position and place a plumb bob from the ceiling to 
the center of the fireplace flue collar. Mark this spot on 
the ceiling. Draw a line through that mark to either side 
of the firebox and indicate dimension X to locate the 
side wall framing. (Fig. 8) Be sure to observe clearance 
requirements for side and parallel combustible walls as 
noted in Figure 20, Page 15.

FP555CR

Insulation

2/26/99   djt

Hard, Flat 

Surface

Insulation

Platform

FP555CR

Fig. 7

 Insulation between platform and fireplace.

Offset Installation

In order to clear an obstruction, it may be necessary 
to offset chimney from vertical. This is accomplished 
by using CFM Corporation elbows. Use the 

30° Offset 

Elbow

 table on Page 5 to determine proper offset and 

parts required.
Each offset requires two (2) elbows. The second elbow 
is equipped with support straps. It is very important to 
install the second elbow in each offset as close to the 
ceiling or support as possible so the elbow straps can 
be secured to framing members to help support the 
weight of the chimney.
Determine offset distance of your chimney arrangement 
from centerline of fireplace to centerline of chimney 
where it is to pass through ceiling.
Locate center point of the chimney on ceiling as though 
a straight up chimney arrangement is to be used. 
Measure your offset dimension from the chimney center 
point on the ceiling.

Fig. 8 

 Locate centerline of chimney with plumb line.

WF556CR

CR Series

LOCATE CENTER LINE

2/19/99   djt

Chimney Centerline

Actual Centerpoint

Plumb Line

10

³⁄₈

(264mm)

Plumb Bob

Imaginary Center-

point

FP556CR

Содержание CR36R

Страница 1: ...R36R CR36L CR Series Corner Woodburning Fireplace DO NOT DISCARD THIS MANUAL Retain for future use For use in U S Canada Underwriter s Laboratories Report No MH6018 20001316 4 07 Rev 14 Homeowner s In...

Страница 2: ...ed or approved by CFM Corpo ration in combination or assembly with a CFM Corporation replace system notwithstanding any independent testing laboratory or other third party approval of such component p...

Страница 3: ...m 21 545mm 172mm 36 914mm 40 1019mm 1054mm Gas Line Access 9 241mm 8 203mm 7 178mm 14 362mm 4 Dia Outside Air Collar Rough Opening Height CR36R L Series Woodburning Fireplace Fig 1 CR36R L Series spec...

Страница 4: ...n Grate Firebox Outside Air Control Outside Air Cover Plate Gas Access See Figure 20 on page 15 for clearance information Outer Dome Ceiling Level Firestop Batt Insulation cut out around restop Fig 2...

Страница 5: ...himney exit at top CR36L R Series Maximum 90 0 Minimum Without elbows 14 0 With 2 elbows 15 0 With 4 elbows 21 0 B Do not use more than four elbows per chimney Attach the straps of the top elbows to a...

Страница 6: ...the surface of the roof a distance of 10 3 m from the chimney in a horizontal plane The top of the chimney must be at least 2 610 mm above the reference point but never less than 3 914 mm in height a...

Страница 7: ...ossible Insulate base of replace with a non combus tible insulation rated for a minimum of 300 F Insulating is very important for outside wall installations over a concrete slab If replace is installe...

Страница 8: ...and indicate dimension X to locate the side wall framing Fig 8 Be sure to observe clearance requirements for side and parallel combustible walls as noted in Figure 20 Page 15 FP555CR Insulation 2 26 9...

Страница 9: ...rip must be fabricated and used to protect combustible surfaces in front of the replace This Z shaped safety strip is not provided but must be fabricated of metal with each horizontal leg at least 1 3...

Страница 10: ...alling the Firestop Spacer in the Ceiling Hole A restop spacer is used to keep pipe spaced properly and required for safety Nail the restop spacer at each corner to the framing members of the ceiling...

Страница 11: ...insulation is planned to be used in the attic Install the attic insulation shield with the anges on its base extending down into the framing hole Nail each corner of attic insulation shield to the fra...

Страница 12: ...predetermined height Check the chimney top installation instructions for details on how high above the roof top the chimney sections all pipes should extend Installing Top Housing or Termination Foll...

Страница 13: ...59mm Min 12 305mm Max 12 305mm Max 7 16 1 1 Fig 18 Fireplace surround ush with nished wall FE101a Combustible Mantel and Trim Mantel Clearance No Noncombustible Facing Material Mantel Clearance with N...

Страница 14: ...lle CERAFORM 126 K 27 1 2 thick re quired 2 CFM Corporation Building Products EH2416 K 458 1 thick required Hearth Installation A hearth extension is required to protect a combustible oor in front of...

Страница 15: ...bustible deco rative covering OR 018 Min Sheet Metal Combustible Floor Minimum Insulation Value R Fireplace Hearth FS108 Sealing Sides 6 22 99 djt Safety Strips must be Overlapped Min Seal Crack Betwe...

Страница 16: ...seal between the pipe and the tube NOTE The gas pipe should not come in contact with any wood structures until it has reached a point at least one 1 inch away from the replace side NOTE Local codes m...

Страница 17: ...42 20001183 5a Screen Rod Finished 90 7554156 7554155 5b Screen Rod Finished Straight 7554181 7554181 6 Screen Pulls two per replace 5584139 5584139 7a Firebrick Side 20000793 20000794 7b Firebrick Ba...

Страница 18: ...he system If you use an unapproved component or make any modi cations you may possibly cause a re hazard and will void the CFM Corporation warranty In addition such action may void the coverage provid...

Страница 19: ...alvanized steel unit Roof ashing is included Appropri ate adapter is required See Sections 2 and 3 Required to extend Traditional Top Housings on steeply pitched roofs Used to terminate chimney at the...

Страница 20: ...n the roof Flashing not included For use with CFM Corporation Type SK8 Chimney Systems Used to terminate chimney at the top of a chase Adapter kit included Flashing not included 8 6 12 8 ue 0 to 6 12...

Страница 21: ...25r Adapter kit CTSK42 3 5 99 djt Chase Top Adapter Kit Hearth Patching Kit 325p r P325p Chase top housings SKDSBL PKDSBL 4 28 99 djt Accessories for Canada Accessory Description Model No Attic Insula...

Страница 22: ...22 CR Series Woodburning Fireplaces 20001316...

Страница 23: ...installed in the continental United States the state of Alaska and Canada only if and so long as the Fireplace is installed or serviced by a quali ed installer preferably NFI or WETT Canada certi ed...

Страница 24: ...410 Admiral Blvd Mississauga Ontario Canada L5T 2N6 800 668 5323 www cfmcorp com CFM Corporation...

Отзывы: